Development (Emergency Electricity Generation) Act 2022
What is this act about?
Is éard atá sa dlí seo ná bearta éigeandála chun forbairt giniúna leictreachais a éascú chun slándáil an tsoláthair leictreachais sa Stát a fheabhsú agus a chosaint, mar gheall ar chúinsí eisceachtúla sa mhargadh agus ar an staid san Úcráin. Díolmhóidh sé forbairtí sonracha ó fhorálacha áirithe den Acht um Pleanáil agus Forbairt 2000 agus ó Threoir um Measúnacht Tionchair Timpeallachta an AE.
Who it applies to: EirGrid, nó aon duine eile, a fhéadfaidh iarratas a dhéanamh ar fhorbairtí giniúna leictreachais; An tAire Comhshaoil, Aeráide agus Cumarsáide, a dhéanann cinntí maidir le ceadú forbartha.
At a glance
- Country
- Ireland
- Area of law
- Energy and network industries
- Articles
- 12
- Source
- irishstatutebook.ie
- Text retrieved
- Explanation updated
What does this act regulate?
- Forbairtí giniúna leictreachais éigeandála sealadacha.
- Díolmhú na bhforbairtí seo ó fhorálacha an Achta um Pleanáil agus Forbairt 2000.
- Díolmhú na bhforbairtí seo ó fhorálacha na Treorach um Measúnacht Tionchair Timpeallachta (2011/92/AE arna leasú).
- Socruithe le haghaidh measúnuithe malartacha comhshaoil agus measúnuithe iomchuí do na forbairtí seo.
Who does this act apply to?
- EirGrid, nó aon duine eile, a fhéadfaidh iarratas a dhéanamh ar fhorbairtí giniúna leictreachais.
- An tAire Comhshaoil, Aeráide agus Cumarsáide, a dhéanann cinntí maidir le ceadú forbartha.
What are the key points?
- Féadfar suas le 450 meigeavata de ghléasra giniúna leictreachais éigeandála sealadach a shuiteáil ag dhá shuíomh ar leith (Shannonbridge agus Tarbert nó suíomhanna malartacha).
- Ní bheidh feidhm ag forálacha an Achta um Pleanáil agus Forbairt 2000 maidir leis an bhforbairt ainmnithe.
- Tá an fhorbairt ainmnithe díolmhaithe ó fhorálacha na Treorach um Measúnacht Tionchair Timpeallachta, mar chás eisceachtúil faoi Airteagal 2(4) den Treoir sin.
- Déanfaidh an Bord measúnú ar an bhforbairt ainmnithe chun cuspóirí na Treorach um Measúnacht Tionchair Timpeallachta a chomhlíonadh agus measúnú iomchuí faoi Rialacháin 2011.
Energy and network industries
Legal text
Legal text
Development (Emergency Electricity Generation) Act 2022 Skip to content Disclaimer Feedback Helpdesk Gaeilge Léim go dtí an t-ábhar Séanadh Aiseolas Deasc chabhrach English Gaeilge English Produced by the Office of the Attorney General Táirgthe ag Oifig an Ard-Aighne Home Legislation Acts of the Oireachtas Statutory Instruments Pre-1922 Legislation Constitution External Resources Bills (Houses of the Oireachtas) Iris Oifigiúil / Official Gazette Revised Acts (LRC) Classified List of Legislation (LRC) Translations (acts.ie) Translations (Houses of the Oireachtas) Government Publications for Sale EU Law (EUR-Lex) FAQ Disclaimer Feedback Helpdesk Search Baile Reachtaíocht Achtanna an Oireachtais Ionstraimí Reachtúla Reachtaíocht Réamh-1922 Bunreacht Acmhainní Seachtracha Billí (Tithe an Oireachtais) Iris Oifigiúil Achtanna Athbhreithnithe (CAD) (An Coimisiún um Athchóiriú an Dlí) Liosta Rangaithe Reachtaíochta Aistriúcháin (achtanna.ie) Aistriúcháin (Tithe an Oireachtais) Foilseacháin Rialtais ar Díol Dlí AE (EUR-Lex) CCanna (Ceisteanna Coitianta) Séanadh Aiseolas Deasc chabhrach Cuardach TitleTeideal Year(s) or rangeBliain nó blianta nó raon TypeCineál All Legislation Acts Statutory Instruments Advanced SearchCuardach Casta HomeBaile ActsAchtanna 2022 Development (Emergency Electricity Generation) Act 2022 Development (Emergency Electricity Generation) Act 2022 Permanent Page URL View by SectionAmharc de réir Ailt View Full ActAmharc ar an Acht Iomlán Bill History Stair Bille Commencement, Amendments, SIs made under the Act Tosach Feidhme, Leasuithe, IRí arna ndéanamh faoin Acht Open PDFOscail PDF Print Full ActPriontáil an tAcht Iomlán Number 35 of 2022 DEVELOPMENT (EMERGENCY ELECTRICITY GENERATION) ACT 2022 CONTENTS
Section 1
Section 2
Section 3
Section 4
Section 5
Section 6
Section 7
Section 8
Section 9
Section 10
Section 11
Section 12
Definitions 1. In this Act— “applicant” means an applicant under section 4 for an approval under section 7 ; “Board” means An Bord Pleanála; “designated development” means development designated by section 2
Designation of development 2. (1) Development comprising of the installation of up to 450 megawatts of temporary emergency electricity generation plant, site development and works ancillary to that installation, and the operation of the plant, intended to be located at two separate sites at Shannonbridge and Tarbert generating stations or at alternative appropriate sites, which development is required urgently for the purpose of ensuring and protecting security of electricity supply by Winter of 2023 to 2024, is hereby designated for the purposes of this Act, in particular section 5 .
Disapplication of Planning and Development Act 2000 to designated development 3. None of the provisions of the Planning and Development Act 2000 shall apply to the designated development.
Application to Minister 4. EirGrid, or any other person, may apply to the Minister, in accordance with the requirements of this Act and such procedures as may be prescribed, for approval under section 7 to carry out the designated development.
Arrangements for Environmental Impact Assessment 5. (1) Without prejudice to the generality of section 3 , the designated development shall be exempt from the provisions of the Environmental Impact Assessment Directive on the basis that the designated development is an exceptional case for the purposes of Article 2(4) of that Directive and the application of those provisions would adversely affect the purpose, referred to in section 2
Arrangements for Appropriate Assessment 6. (1) On receiving an application under section 4 , the Minister shall arrange for an assessment of the designated development to be carried out by the Board in accordance with Part 5 of the Regulations of 2011, subject to any modifications as to process as may be prescribed for the purposes of this Act, and Part 5 of those Regulations shall apply in respect of the designated development subject to such modifications.
Decision of Minister 7. (1) The Minister may, having considered an application made to him or her under section 4 for an approval under this section, having taken into account the assessments carried out by the Board under sections 5
Requirement to comply with approval 8. The designated development shall be carried out in accordance with an approval under paragraph (a) or (c) of section 7
Regulations for purpose of Act 9. (1) The Minister may prescribe such matters of procedure and administration as appear to the Minister to be necessary or expedient in respect of this Act.
Section 15 of Climate Action and Low Carbon Development Act 2015
Expenses 11. The expenses incurred by the Minister in the administration of this Act shall, to such extent as may be sanctioned by the Minister for Public Expenditure and Reform, be paid out of moneys provided by the Oireachtas.
Short title and commencement 12. (1) This Act may be cited as the Development (Emergency Electricity Generation) Act 2022.
1 OJ No. L26, 28.1.2012, p.1 2 OJ No. L24, 25.4.2014, p.1 3 OJ No. L206, 22.7.1992, p.7 4 OJ No. L26, 28.1.2012, p.1 5 OJ No. L24, 25.4.2014, p.1 6 OJ No. L206, 22.7.1992, p.7 7 OJ No. L305, 8.11.1997, p. 42 8 OJ No. L284, 31.10.2003, p. 1 9 OJ No. L363, 20.12.2006, p. 368 10 OJ No. L158, 10.6.2013, p. 193 Privacy Statement Accessibility European Legislation Identifier (PDF) Open Data License Ráiteas Príobháideachais Inrochtaineacht Aitheantóir Eorpach Reachtaíochta (ELI) Ceadúnas Sonraí Oscailte Liosta Fianán © Government of Ireland. Oireachtas Copyright Material is reproduced with the permission of the Houses of the Oireachtas © Rialtas na hÉireann. Atáirgtear ábhar faoi Chóipcheart le cead ó Thithe an Oireachtais