PAPA IOANNIS ZOGRAPHAKIS ν. EFTYCHIA AGATHOCLEOUS (V20) 1 CLR 31 ΠΑΓΚΥΠΡΙΟΣ ΔΙΚΗΓΟΡΙΚΟΣ ΣΥΛΛΟΓΟΣ CyLaw | Αναφορικά μ'εμάς | " target="_top">Επικοινωνία | Όροι χρήσης Έρευνα - Κατάλογος Αποφάσεων - Εμφάνιση Αναφορών (Noteup on) - Αρχείο σε μορφή PDF - Αφαίρεση Υπογραμμίσεων (V20) 1 CLR 31 1954 January 9 [HALLINAN, C.J., AND ZEKIA, J.] PAPA IOANNIS ZOGRAPHAKIS, Appellant, v. EFTYCHIA AGATHOCLEOUS, Respondent. (Civil Appeal No. 4049) Limitation of Actions-Contract Law, section 63-Verbal agreement to extend time for performance-Effect on operation of Limitation of Actions Law. On 1st June, 1942, the appellant sold a building plot to the respondent; part of the price was paid and part was to be paid within two years. Because of difficulties with various public authorities the appellant was unable to transfer the land to the respondent; on several occasions the respondent agreed to postpone the execution of the contract by the appellant; finally in 1953 he transferred the land to his daughter; whereupon the respondent sued for breach of the contract. The trial Court held that the claim was not statute barred and gave judgment for the respondent. Upon appeal, Held : A verbal agreement to extend the time for performance made before the time for performance had arrived (and therefore before the right to sue accrued) would, under section 63 of the Contract Law, have postponed the right to sue and prevented the Limitation of Actions Law from running against the respondent; but a verbal agreement after the right to sue had accrued would not stop the statute from running. The respondent had not proved that such verbal agreement was made before the right to sue accrued; her right was therefore statute barred. Appeal allowed. Appeal by defendant from the judgment of the District Court of Limassol (Action No. 176/53) in favour of plaintiff. G. Cacoyannis for the appellant. A. Anostossiades with A. Myrianthis for the respondent. Judgment was delivered by the Chief Justice. A separate judgment was delivered by ZEKIA, J.: HALLINAN, C.J.: On the 1st June, 1942, the appellant in this case agreed to sell a building plot at Polemidhia to the respondent for the sum of £30. Respondent paid part of the purchase price and, according to the terms of the agreement, she was to pay the balance within two years; upon such payment the appellant was to transfer the property to respondent. The respondent was at all times willing and ready to pay the balance but the appellant for various reasons was unable to proceed with the sale. The trial Court found on sufficient evidence that the parties on several occasions between the date of the agreement and the commencement of these proceedings had agreed that the date by which the agreement should be performed be extended, but all these agreements were made orally. Finally, at the beginning of 1953, the appellant informed the respondent that, because he could not get permission to divide up the land part of which he had sold to the respondent, he had transferred the land to his daughter. If it can be held that an enforceable agreement was in existence between the parties at the beginning of 1953 then the action of the appellant had clearly constituted a breach of that agreement. The appellant however contends that the respondent's claim is statute barred. He submits that the respondent's right of action accrued in 1944 by which time the contract of 1942 was due to be performed. Against this contention it is submitted by the respondent that the original contract was varied as to the time for performance by additional agreements which (although they would not be enforceable under English law for lack of consideration) are enforceable under section 63 which follows section 63 of the Indian Contract Law and which is a notable departure from the English Law of Contract. This section provides that a promisee, inter alia, may extend the time for the performance of a contract. By agreeing to extend the time for performance, it is submitted that the parties have agreed that the right of action shall not accrue until the time for performance has arrived. In English law where a promisee allows the promisor to delay the performance of the promise, this does, not prevent the promisee from revoking his concession and suing on the contract; his right of action has accrued and he is not stopped from enforcing it since he has not given an enforceable promise. Indeed according to Anson on Contract (18th Edition) p. 321 "a mere postponement of performance for the convenience of one of the parties, does not either discharge or vary the contract". Having regard to section 63 of our Contract Law, we agree with the respondent's submission that an agreement to extend the time for performance postpones the right of action accruing and consequently postpones the statute running against the promisee. But the result is not the same if the time is extended after the right of action has accrued. The Limitation of Actions Law will then continue to run unless there is an acknowledgment of this right of action so as to satisfy the provisions of section 6 of that Law. The fact that in Cyprus agreements under section 63 of the Contract Law can be made without consideration should make the Courts regard the evidence of such agreements with caution and require strict proof from the party on which the burden lies. For the object of the Limitation of Actions Law (which is to prevent litigation brought to enforce stale claims) would in many cases be defeated if a promisee could lightly set up a parole agreement to extend the time for performance so as to prevent the right of action accruing. In the present case the burden of proving this oral agreement was on the respondent as promisee. In her evidence she alleges that the first request by the appellant to defer performance was "in May or June, 1944". Now the right of action accrued on 1st June, 1944, and it cannot be said that the respondent has discharged the burden of proof that lay on her to show that the agreement to extend the time for performance was made before the right of action accrued. Once the right of action accrued in June, 1944, any subsequent agreement short of an acknowledgment in writing could not prevent the period of limitation from running against the promisee. For the respondent is not suing on the subsequent agreement, but on the original contract. The subsequent agreement does not constitute the cause of action; at the most it merely varies a term (i.e. the time for performance) in the original contract. Since any acknowledgment has to be in writing under section 6
Επεξήγηση AI βάσει του επίσημου κειμένου του νόμου. Ενδεικτική, δεν υποκαθιστά νομική συμβουλή.