← Ireland

2026 IEHC 342

Obsah (8)§128§96§133§175§121§36§32§5

[2026] IEHC 342 THE HIGH COURT PLANNING & ENVIRONMENT CIRCUIT APPEAL DUBLIN CIRCUIT COUNTY OF THE CITY OF DUBLIN [High Court Record No.: H.CA.2025.0000329] [Circuit Court Record No.: 2025 5748 Co. Dub

tempt to create a fait accompli with a view to turning around and defiantly asking the 3 system, in effect, “what are you going to do about it?”. I suppose like many other people who defy planning law, the respondents are now going to find out. 2. The old adage is that when the facts are against you, hammer the law – and nobody could take from the vigour of the hammering resorted to by the respondents in that regard. While a superhuman jurisprudential effort has been made on behalf of the respondents to advance any conceivable reason as to why the facts should not lead to an adverse order, that exercise, while

one level enormously impressive, is, unpersuasive. As the council submitted, “this isn’t a marginal case”. The ultimate reason for that is that while ornate scholarly infrastructure was totteringly erected by the respondents in a majestic doctrinal exercise by way of defence, none of this arises on the facts and therefore none of this makes any difference to anything. What defeats the respondents is not some abstruse point of law that cries out for clarification, but the egregious nature of their own conduct and the inevitably adverse factual findings that flow from that. Judgment history

  1. A 1972 permission required the removal of caravans within one year, but this was not complied with. It also prohibited additional caravans. When the council sought to enforce this against the previous owner Mr Hill, they were unsuccessful: Dublin County Council v. Hill [1994] 1 I.R. 86, [1992] I.L.R.M. 397 per McCarthy J. (ex tempore, O’Flaherty and Egan JJ. concurring).
  2. During the Circuit Court proceedings, the appellants issued judicial review proceedings seeking to restrain s. 160 proceedings but apparently without disclosing the existing s. 160 proceedings on the papers (Threshford Limited and Mullnassa Limited v South Dublin County Council [Record No. 2025 1624 JR]). The appellants, the first time the matter was before the court, applied to withdraw those proceedings. Notwithstanding the application to withdraw the said proceedings the council sought to address the High Court (Holland J.), and I deal with this further below. Ultimately the judicial review application was struck out.
  3. Section 160 injunctions were granted by HH Judge O’Connor on 19 December 2025, and the respondents appeal from those orders. Geographical context
  4. The proceedings comprise an appeal by the first and second named appellants against a s. 160 order made by Dublin Circuit Court on 19 December 2025 and perfected on 22 December 2025 in relation to lands located

Chianti Park, Mount Seskin Road, Raheen, Brittas, Co Dublin,

: https://maps.app.goo.gl/5TAAWEjDT1VqLmDMA. The lands are zoned “High Amenity- Dublin Mountains (HA-DM)” in the South Dublin County Development Plan 2022-

  1. The property the subject of these proceedings can be viewed on Google Street View using https://maps.app.goo.gl/pnLXdfk8VTya5ALaA. An aerial photo of the property from Google Maps can be accessed

https://maps.app.goo.gl/2S42xG7Vq8QWkVq36 .

  1. Next door to Chianti Park is a development called Hillbrook Lawns which is a similar caravan/ mobile home park since
  2. The respondents say that the next door park demonstrates that the modular dwellings may be of a superior type of structure to caravans/ mobile homes for the purposes of living conditions. Parties
  3. The plaintiff/respondent, South Dublin County Council, is the relevant planning authority.
  4. John O’Neill is the applicant/plaintiff in these proceedings. He lives c. 200 m from the property the subject of these proceedings.
  5. As to the respondents, Threshford Limited, of College House, 71/73 Rock Road, Black Rock, Co. Dublin (A94 FPXP), is the owner and/or occupier of the lands and/or is the entity responsible for carrying out the development the subject of proceedings pursuant to s. 160 of the Planning and Development Act 2000 (the 2000 Act).
  6. Mullnassa Limited, of College House, 71/73 Rock Road, Black Rock, Co. Dublin (A94 FPXP), is the owner and/or occupier of the lands and/or is the entity responsible for carrying out the development the subject of proceedings pursuant to s. 160 of the 2000 Act.
  7. Branach Developments Limited, of Thomastown, Caragh, Kildare, Ireland, is the entity carrying out the development on the lands on behalf of the first and second named appellants. Facts – SDCC case
  8. The alleged unauthorised development, the subject matter of these proceedings, gave rise to a series of complaints from mid-August 2025 to mid-September
  9. On 18 August 2025, pursuant to s. 152 of the 2000 Act, the council issued warning letters to Mr Hill (the previous owner of the lands) and the third named appellant.
  10. The previous owner responded to the said warning letter, indicating he was no longer the owner of the lands.
  11. The third named appellant responded to the council by letter dated 12 September 2025, indicating that whilst they were carrying out the works on the lands, it was

the request/instruction of the owner. 4

  1. The council subsequently issued a letter to various parties, including the appellants herein, prior to proceedings. Dated 30 September 2025, same sought for the unauthorised development to cease immediately, as well as other specific undertakings.
  2. The third named appellant replied to the said letter, by way of correspondence dated 1 October 2025, and again disputed any responsibility for the unauthorised development.
  3. In response to this correspondence, the council wrote to the third named appellant on 1 October 2025, asking it to clarify who the owner of the lands was or who it was working for. By way of further letter, dated 1 October 2025, the third named appellant failed and/or refused to provide this information.
  4. On 2 October 2025, the council received correspondence from solicitors acting for the first and second named appellants. This correspondence indicated that they were seeking time to take instructions.
  5. The council responded to the said correspondence by email dated 3 October 2025, indicating that it would extend time for any undertakings to 6 October 2025

2 pm. 23. On 7 October 2025, the solicitor for the first and second named appellants responded to the council’s correspondence and indicated, for reasons set out, that the appellants’ position was that the allegation of unauthorised development was “misconceived” and the development was exempt pursuant to s. 4

(1)(h) of the 2000 Act. Facts – O’Neill case
  1. The lands the subject of these proceedings are known as Chianti Park, Mount Seskin, Brittas, County Dublin, also referred to as Hillsbrook Lawn, and are situated within the administrative area of South Dublin County Council. The property comprises a former caravan, mobile home and chalet site and is owned by the respondents.
  2. The applicant resides in close proximity to the property and has done so for a number of years. The applicant’s dwelling is located approximately 200 m from the property.
  3. The property was originally in agricultural use. From 1968, allegedly, the property was used for mobile homes and chalets. Planning permission was granted in or about 1972 for the retention of a limited number of mobile homes, subject to conditions including a requirement that the structures be removed within one year and that no further such structures be erected.
  4. Over time, the number of structures on the property increased beyond what was originally permitted, and there has been a history of unauthorised development on the property.
  5. On or about 11 August 2025, works commenced on the property which are the subject of these proceedings.
  6. The works the subject matter of these proceedings are works for the maintenance, improvement or other alteration of existing structures.
  7. On or about 18 August 2025, the council issued a warning letter in respect of the said works.
  8. On 19 September 2025, the applicant made a complaint to the council in relation to the works being carried out on the property and was informed of the warning letter issued on 18 August
  9. By correspondence dated 23 September 2025, the applicant’s solicitors wrote to the council seeking information as to what further steps, if any, had been taken by the council in respect of the said works. No reply was received.
  10. By letter dated 2 October 2025, the applicant’s solicitors wrote to the respondents noting that no planning permission had been granted for the development and calling upon the respondents to cease all works on the property. The respondents were requested to confirm the basis upon which the development was said to be authorised and were put on notice that injunctive relief would be sought in the absence of an undertaking to cease works. No reply was received.
  11. By further correspondence dated 21 October 2025, the applicant’s solicitors wrote to the second named respondent in similar terms. No reply was received.
  12. Notwithstanding the absence of any planning permission and the said correspondence, the works on the property continued. The works carried out include the demolition of existing caravan/ mobile home/ chalet-type structures, the clearance of significant areas of the site, and the construction of new modular dwellings, including on previously undeveloped areas of the property.
  13. The works have also resulted in impacts on adjoining lands, including runoff from the property which has affected drainage

the applicant’s dwelling.

  1. On 3 November 2025, the applicant instituted proceedings pursuant to s. 160 of the 2000 Act seeking to restrain the said unauthorised development and to restore the property to its prior condition.
  2. On or about the same time, without notice to the applicant, the council instituted separate proceedings pursuant to s. 160 of the 2000 Act in respect of the same property.
  3. The applicant’s position is that the development is unauthorised development and is not exempted development. 5
  4. The respondent/defendants position is that development is exempted development pursuant to s. 4

(1)(h) of the 2000 Act.
  1. Both sets of s. 160 proceedings were heard together on 4 and 9 December
  2. On 19 December 2025, the Circuit Court delivered judgment and made orders restraining the unauthorised development and directing relief pursuant to s.
  3. The respondents appealed the said orders to the High Court on 19 December 2025, and sought an interim stay. A limited stay was granted by Ms Justice Farrell on 19 December 2025, permitting certain specified weatherproofing works to be undertaken and directing that photographic evidence of such works be furnished. Procedural history – SDCC case
  4. The proceedings were issued in Dublin Circuit Court on 24 October
  5. The council, by way of ex parte application on 30 October 2025 – which the appellants appeared

and addressed the court on – sought interim relief and/or short service for an application for interlocutory relief to be heard

the earliest possible date.

  1. The Circuit Court (HH Judge O’Connor) made the interlocutory application returnable for the following week – 6 November
  2. On 5 November 2025, the appellants issued a notice of motion to transfer the proceedings to the High Court on the basis that it was contended that the market value of the lands exceeded the Circuit Court’s jurisdiction.
  3. Due to time constraints, the Circuit Court was unable to hear the interlocutory application on 6 November 2025, and the matter was adjourned to the following week to fix an early hearing date for the substantive case.
  4. On 7 November 2025, the council, without prejudice to its position that the market value of the Lands was within the jurisdiction of the Circuit Court, indicated to the appellants that it would consent to the proceedings being transferred to the High Court (with a view to having same determined as expeditiously as possible in the Planning and Environment List). The council appeared before the Circuit Court to seek an order to this effect on 7 November 2025, however the appellants informed the court, that they were withdrawing their motion (costs were awarded against them for same) in circumstances where the Circuit Court had listed the matter to fix an early hearing date.
  5. Following the close of pleadings (exchange of affidavits) and following the substantive hearing of the matter on 4 December 2025 (2 hours) and 9 December 2025 (2 hours), on 19 December 2025, the Circuit Court made an order granting a planning injunction in the terms outlined in the order under appeal.
  6. On 19 December 2025, the appellants lodged the within appeal on the same day and sought a stay on the Circuit Court order from the High Court (Farrell J.). The appellants were granted a very limited stay which allowed them to carry out some minor weather-proofing to two structures on the lands.
  7. For the purposes of their appeal, the appellants have filed two additional affidavits, the second affidavit of Keith McDermott and the affidavit of Ann Mulcrone. This was on a de bene esse basis and the council maintained an objection to that.
  8. Without prejudice to the council’s objections to the admissibility of same, the council filed a replying affidavit from Cian Harte on 15 April
  9. The council served its legal submissions, input into this statement of case and input index of authorities on the appellants on 28 April
  10. The appellants served their legal submissions, input into this statement of case and input index of authorities on the council on 8 May
  11. The appeal was heard on 13 May 2026 together with the related case 2025 5894 CA (the O’Neill proceedings). Procedural history – O’Neill case
  12. The applicant instituted proceedings seeking an interim injunction before the Circuit Court on 3 November
  13. Interim relief was refused, and the matter was listed for the hearing of an application for interlocutory relief on 6 November
  14. On or about the same time, South Dublin County Council instituted separate proceedings pursuant to s. 160 in respect of the same property. The applicant had been unaware of such proceedings.
  15. On 5 November 2025, the respondents issued a motion seeking to transfer the proceedings to the High Court on the basis, inter alia, of the alleged value of the property.
  16. On the return date of 6 November 2025, issue was raised by the respondent as to the jurisdiction of the Circuit Court to deal with both sets of proceedings by reference to the alleged value of the property. The court rose to enable South Dublin County Council and the respondents to consider matters. The application for an interlocutory injunction was not heard and no undertaking was made by the respondents not to undertake further works. 6
  17. On 7 November 2025, the applicant indicated to the Circuit Court his consent to the transfer of the proceedings to the High Court. The respondents however subsequently withdrew the motion to transfer and agreed that the proceedings would continue in the Circuit Court.
  18. On 11 November 2025, the costs of the respondents’ motion to transfer the proceedings to the High Court were awarded to the applicant with no stay.
  19. On 13 November 2025, directions were given for the full hearing of the proceedings, including directions as to the exchange of affidavits, the matter being fixed for hearing on 4 December 2025 and 9 December
  20. The respondents did not comply with the directions for filing an affidavit.
  21. The proceedings were called on for hearing on 1 December 2025 in the Circuit Court.
  22. The respondent furnished unsworn replying affidavits to the applicant on 4 December
  23. The applicant objected to the introduction of those affidavits in breach of the court’s directions. They were admitted by the court on 4 December
  24. The hearing continued, and concluded on 9 December 2025 with the court reserving judgment and requesting that the respondents respect the court’s wish that no further work be carried out pending delivery of judgment.
  25. On 15 December 2025, the applicant informed the court that, inter alia, deliveries of sand had been made to the property subsequent to 9 December
  26. The court indicated that judgment would be brought forward to be delivered on 19 December
  27. On 19 December 2025, the Circuit Court delivered judgment and made orders restraining the unauthorised development and directing relief pursuant to s. 160 of the 2000 Act.
  28. The respondents appealed the said orders on 19 December 2025, and sought an interim stay from Ms Justice Farrell. Ms Justice Farrell granted a limited stay permitting certain specified weatherproofing works only and directing that photographic evidence of such works be furnished. The matter was listed for mention from time to time thereafter.
  29. The matter was listed for hearing together with the related case 2025 0329 CA on 13 May
  30. Post-hearing procedural history
  31. Judgment was reserved

the end of that hearing. I would like to record my thanks to all of the lawyers involved for their unfailingly courteous, professional and helpful assistance. As I have previously sought to make clear, insofar as any points advanced are not being accepted in this or any other given judgment, that is solely to do with the inherent merits of such points and is no reflection on those instructed to convey such points, a distinction that most certainly should be, and I believe generally is in fact, self-evident to all concerned. 72. On 22 May 2026, a draft of the present judgment was sent to the parties, pursuant to paras. 15, 195 to 198 and 204 of Practice Direction HC 137, to give an opportunity to address matters such as errors/ ambiguities on the basis set out below. 73. Parties are required to: (

  1. i)Read the draft or have their legal representatives if applicable do so on their behalf. (
  2. ii)Identify any matters falling within the below. (iii) Positively communicate with the court in writing in response to the draft by the deadline specified, such responses to be emailed to the court and uploaded to ShareFile, either stating that they have no comments or setting out the comments. (
  3. iv)Carry out the foregoing without delay - the draft judgment procedure is a concession which parties can engage with but must do so with immediate dispatch, discipline and focus – it is not the opening of a new phase of the litigation that gives rise to “an entitlement to elaborate procedures

every point” (to use a phrase of O’Donnell C.J. (Dunne, Charleton and Baker JJ. concurring) in O’Sullivan v. Health Service Executive [2023] IESC 11 (Unreported, Supreme Court, 10 May 2023)

para. 39); and still less should the procedure invite the perhaps “serious error, to which lawyers are prone, to approach any such case on the tacit assumption that only procedures which approximate to a criminal trial are fair, and anything which departs from that is somehow dubious” (O’Donnell J. (Clarke C.J., McKechnie, MacMenamin, Dunne JJ. concurring) in O’Sullivan v. Sea Fisheries Protection Authority [2017] IESC 75, [2017] 3 I.R. 751, [2018] 1 I.L.R.M. 245, 780). (v) Keep the draft confidential. Draft judgments are not public domain materials and, while they can be shared between the lawyers concerned and their clients, subject to the following, it is inappropriate for any person to refer to them for any purpose other than to assist the court in relation to the finalisation of the formal judgment. Therefore anyone with information as to the text, content or proposed outcome of any draft is required not to publish or transmit such information to others save solely by way of private transmission for the legitimate purposes of assisting in the finalisation of the judgment and subject to a similar restriction on any recipient. 7 Trial participants should take reasonable steps to keep drafts confidential. On this topic, see

torney General v. Crosland (No. 2) [2021] UKSC 58, [2022] 1 W.L.R. 367, [24/01/2022] T.L.R. 1 (Briggs, Kitchin, Burrows, Rose, Arden SCJJ) which discusses why restriction on publication of draft judgments is in the interests of the administration of justice; see also Baigent v. Random House Group Ltd [2006] EWHC 1131 (Ch), [2006] 5 WLUK 45,

(2006)150 S.J.L.B. 603 (Smith J.); R. (Counsel General for Wales) v. Secretary of State for Business, Energy and Industrial Strategy [2022] EWCA Civ 181, [2022] 1 W.L.R. 1915, [2022] 4 All E.R. 599 (Sir Geoffrey Vos MR; Davies and Dingemans LJJ. concurring); Public Institution for Social Security v. Banque Pictet & Cie SA and others [2022] EWCA Civ 368, [2022] 3 WLUK 291, [2022] B.L.R. 349 (Carr LJ; Jackson and Simler LJJ. concurring); Itkin v. Wood [2023] JRC 101 (Unreported, Royal Court of Jersey, 22 June 2023). 74. The foregoing constitutes an immediately effective direction of the court to the parties and anyone having notice of the draft judgment with effect from the date of circulation of the draft. 75. The responses should not be to reargue the substance (submissions to that effect will be disregarded) but are confined to matters such as: (
  1. i)informing the court as to whether the party prefers an alternative to a formal written judgment as proposed, and if the party so considers, whether that party considers that the entire matter or some specified part of it can be disposed of (
  2. a)by order without a reasoned judgment, or (
  3. b)by ex tempore reasons without a written judgment; (
  4. ii)informing the court, assuming that the court proceeds with a formal judgment, as to whether the party wishes to propose any corrections to the draft such as: (
  5. a)any apparent typographical, factual, legal or other errors in the draft; (
  6. b)any apparent ambiguity or other matter in the draft that could unnecessarily multiply issues or complicate the further processing of the matter; (
  7. c)any redaction of personal or other information that a party wishes to request; (
  8. d)in the event that the court proposes to refer to any matter (whether factual, legal (including reference to authorities or other legal material), obiter comment or otherwise) not referred to

the hearing, any submission as to why such reference is not relevant or otherwise should not be included or as to why such matter if included should not lead to the proposed conclusion; (

  1. e)any other matter in the draft judgment that the party considers should be omitted; (
  2. f)any matter not included in the draft judgment that the party considers should be added to it (including where the party considers that procedural, factual or legal points not set out in the judgment should be addressed or where the party considers that reasons for any aspect of the decision are not set out or where an overall ground is disposed of but detail of the ground or sub-ground is not expressly addressed, or where an issue arose the disposition of which would be obiter but on which the party concerned considers that there would be a benefit in the court expressing a view); and (
  3. g)any other proposals as to the wording (as opposed to substance) of the decision if the proposed wording causes any issue for a party for any identified reason; and (iii) assisting the court by providing views on such matters if any on which views are specifically invited in the draft judgment. 76. In particular, parties should draw the court’s

tention to any apparent error or ambiguity whether they have been successful on the point or not. 77. The rules of engagement in such a situation are that the draft is without prejudice to the right of the court ultimately to issue a judgment in whatever form or with whatever content it considers appropriate. It is then entirely a matter for the court as to whether to give judgment with or without amendment including any amendment that appears appropriate to the court whether arising from submissions or not. Any judgment may be given without further notice following the expiry of the specified period, whether comments are made or not. That period will not be extended save in exceptional circumstances. 78. The deadline for such comments from the parties was to be 16:00 on Wednesday 27 May 2026. Comments were as follows: (

  1. i)SDCC – no changes proposed. (
  2. ii)Applicant in O’Neill – some corrections/ updating of information. (iii) Respondents – sought more time to respond due to Senior Counsel unavailability during vacation. Unfortunately that is not generally a basis for additional time because accepting that rationale would prevent the court from issuing judgments 8 during the vacation, which is an essential safety valve to avoid unsustainable buildup of backlogs. Parties in cases heard near the end of any given term need to have a contingency plan for the totally foreseeable possibility of a draft being issued shortly thereafter. When this application was rejected the respondents then delivered a "notice of appeal” type response. 79. This was, of course, a complete misunderstanding of the procedure, and, I’m afraid, not uncharacteristic of the scattergun approach on behalf of the respondents here. For the record, their response was: “Further thereto, the Appellants would like to address the Court on the following matters prior to the Court finalising its draft judgment. It is respectfully submitted as follows: 1. The Court has failed to have appropriate regard to the nature of the structure which was the subject matter of the works for alteration and improvement 2. The Court has failed to have appropriate regard to the fact that the footprint of the structure has not been increased, nor the dimensions altered beyond what existed on the site which evidence was not contradicted. That evidence was that the foundations of the structure have been retained. That evidence was not cross examined and where there was no contradictory evidence to undermine what was set out in that Affidavit 3. The evidence from the Architect showing the before and after demonstrates that the extent of the alterations as was shown and was not a significant given the surveys carried out by the Architect both before and after. 4. The Court has failed to have appropriate regard to the application of the principle governing Section 4

(1)(h) and in particular the Judgement of Ryan J (as he was then) in Micheal Cronin (ReadyMix) Limited and the subsequent Judgment of the Supreme Court in Cairnduff v O’Connell which gives the effect that there is a greater margin of appreciation shown in a set of works which are exempted development as prescribed under that section and is not confined to insignificant works. 5. The Court errored [sic] in its interpretation of the Defences available under Section 4
(1)(h) as set out in Morris v Garvey the application of which defences apply to the facts of this case where it was a genuine belief based on a statutory exemption which related to no alteration of the character of the structure that would render the development inconsistent with the previous development or adjoining structures.
  1. It is also submitted that the Court errored [sic] in its interpretation of the defence of disproportionate hardship in terms of how it has been applied to the facts of this case.
  2. Whether the finding of the court that this development commenced subsequent to the 1st October 1964 is consistent with the purpose of the Section 160
(6)(7 year rule) of the Planning & Development Act 2000, as amended.
  1. Having regard to the defences raised, whether it is appropriate to make the cost orders contemplated in the draft judgment and in particular to the cost orders contemplated in the O9’Neill [sic] proceedings in circumstances where those proceedings were commenced after the first return date of the SDCC proceedings.
  2. It is submitted that the Court errored [sic] in its interpretation of the reliefs sought by the Applicants and in particular those reliefs relating to the restoration of the lands to their condition immediately prior to the commenced of the development in August
  3. The Court appears to make a finding that the original development consisted of mobile homes only. If that is indeed the finding of the Court, it is disputed by the Appellants.
  4. The Court errored [sic] in its finding that both Affidavits of Ann Mulcrone were inadmissible on the basis that they should have been before the Court of first instance. The Appellants were given liberty to file an Affidavit in the Appeal. The Appellants submit that both affidavits should be admissible in the circumstances and on the basis of their relevance and

the very least should be heard in the question of inadmissibility. The Appellants have had a preliminary preview of the comments to the Court in the O’Neill proceedings in the last few minutes and reserve its position in respect of those comments. The Appellants also confirms that the photographs that were directed to be sent to the parties by Ms Justice Farrell were in fact sent to the parties.”

  1. In fairness to the parties I did extend the period for responses to a full seven days up to 17:00 on Friday 29 May 2026 (the period for corrections started on Friday 22 May 2026) and invited any further responses from the applicants to the foregoing.
  2. The council then responded in the following terms which I generally endorse: “Date: 29th May 2026 Re: SOUTH DUBLIN COUNTY COUNCIL Plaintiff /Respondent -and- 9 THRESHFORD LIMITED, MULLNASSA LIMITED AND BRANACH DEVELOPMENTS LIMITED Defendants/ Appellants Dear Registrar, Re: South Dublin County Council’s Response to the Appellants’ comments on Draft Judgment As to the Appellants’ comments on the Draft Judgment, the Council respond as follows. The Appellants appear to misunderstand the nature and purpose of the Draft Judgment process - this is so notwithstanding the fact that same is clearly set out in the Draft Judgment (§72 et seq). In this regard, the Appellants fail to note that the purpose of the Draft Judgment procedure is not to reargue the substance of the case (Draft Judgment, §76). The Appellants’ ‘points’ on the Draft Judgment ignore this very plain stated purpose and are therefore regrettably a disrespectful

tempt to re-argue the case and are entirely inappropriate. The so called ‘points’ are framed in the language of a notice/grounds of appeal to the same Court of judgment. In substance, the Appellants are inappropriately purporting to treat the Draft Judgment as an opportunity for another appeal (having already appealed from the Circuit Court). A number of general observations can be made in response to the Appellants’ ‘points’ on the Draft Judgment: they are advanced without actually engaging with the Draft Judgment noting that not one point is referrable to any particular paragraph of the Draft Judgment; they are framed, in substance, as (albeit not in any sense compelling or weighty) grounds of appeal; they appear to reflect an unwillingness on the part of the Appellant to accept that on the application of existing case law to the facts of their case, their

tempt to argue that the works were exempted development was completely unsustainable; and they are baseless when one considers the actual terms of the Draft Judgment. The Council also has a broader concern, stemming from the nature of the Appellants’ ‘points’ on the Draft Judgment and the related request to address the Court on same, that the approach being adopted by the Appellants is a rather blatant/obvious

tempt to seek to delay the finalisation of the Orders proposed. Appellants’ Point 1: ‘The Court has failed to have appropriate regard to the nature of the structure which was the subject matter of the works for alteration and improvement.’ Council’s Response: It is not clear what the Appellants point here is by reference to the purpose of the Draft Judgment procedure. In any event, there is no substance to this complaint and same appears to have been made without actually reading the Draft Judgment or, alternatively, in wilful ignorance of same. In this respect, the Council would note: The assertion that the Court failed to have ‘appropriate regard’ to the nature of the structures which was altered or improved, is un-stateable. The Court was clearly aware of the existing structures and new structures on the lands having had all of the relevant exhibits opened to it, including photographs of the existing structures and the new structures, which the Appellants did not dispute or address. This complaint appears to repeat the similar approach adopted by the Appellant in opposing the proceedings - which was one of ignoring the actual evidence and electing to make high level abstract arguments divorced from the facts of the case. The contention is also premised on the Appellants legally misconceived argument, which the Court correctly rejected (inter alia, §130), that the same structure remained on the lands. As the Draft Judgment notes, by reference to a range of cases which the Appellants did not engage with in any meaningful way (either

trial or now in making these misconceived complaints) the ‘total or near-total replacement of a structure is not maintenance, improvement or alteration of the structure’. The Draft Judgment deals with this issue

§128

et seq- where it expressly refers to the photographic evidence adduced from the Council (§130, §133, and §135) - this included images of what were there previously and what is now there. Appellants’ Point 2: ‘The Court has failed to have appropriate regard to the fact that the footprint of the structure has not been increased, nor the dimensions altered beyond what existed on the site which evidence was not contradicted. That evidence was that the foundations of the structure have been retained. That evidence was not cross examined and where there was no contradictory evidence to undermine what was set out in that Affidavit.’ Council’s Response: Again it is unclear what the Appellants point here is by reference to the purpose of the Draft Judgment procedure. There is no substance to this complaint - which is again unhelpfully advanced without actually referring to or engaging with the content of the Draft Judgment or the evidence before the Court. The points made in response to Point 1 also apply here. In addition, this point appears to repeat the error which informed the Appellants approach in the case - continuously asserting that their evidence was not contradicted - it was expressly contradicted by the Council, the Appellants just elected not 10 to engage with same. This is relevant to the Court’s findings that the Appellants have failed to discharge the burden of proof which rests on them to established exempted development. Relevantly, the Draft Judgment addresses these points:

§96

et seq- the Court expressly noted that averments made by Mr Donoghue fly in the face of reality and highlighted the lack of weight that could be

tached to his evidence (a point which the Appellants don’t dispute - illustrating the misplaced nature of the points they now seek to make on the Draft Judgment).

§133et seq- there was no failure to have appropriate regard to anything.

Further, the point has to be considered in light of the findings made about Mr Donoghue’s Affidavit - which the Appellants notably fail to address in their comments on the Draft Judgment. Appellants’ Point 3: ‘The evidence from the Architect showing the before and after demonstrates that the extent of the alterations as was shown and was not a significant given the surveys carried out by the Architect both before and after’. Council’s Response: It is not clear what the Appellants point here is by reference to the purpose of the Draft Judgment procedure. To compound matters, this ‘point’ invokes Mr Donoghue’s misplaced invocation of the ‘Architect’ title, an issued addressed in the Draft Judgment ( §95 et seq). This is worrying in circumstances where the Appellants appeared to accept during the course of the hearing that this was incorrect and offered to file a correcting affidavit (which they did not do). As outlined above, by reference to the Draft Judgment, the Appellants do not actually say what the point here is - noting that Mr Donoghue’s evidence was contradicted by the Council and rejected by the Court. Simply stating that Mr Donoghue gave certain evidence (which is all this point does), which the Court was aware of and which the Court addressed, does not enlighten anyone as to what the issue is with the Draft Judgment (and there is no issue). Appellants’ Point 4: ‘The Court has failed to have appropriate regard to the application of the principle governing Section 4

(1)(
  1. h)and in particular the Judgement of Ryan J (as he was then) in Micheal Cronin (ReadyMix) Limited and the subsequent Judgment of the Supreme Court in Cairnduff v O’Connell which gives the effect that there is a greater margin of appreciation shown in a set of works which are exempted development as prescribed under that section and is not confined to insignificant works.’ Council’s Response: It is not clear what the Appellants point here is by reference to the purpose of the Draft Judgment procedure. Certainly the procedure is not one that permits an unsuccessful party to ignore the actual text of the Draft Judgment and complain that cases were not considered when they clearly and expressly where. This point is just wrong - the Court did have regard to these authorities and other relevant authorities ( which the Appellants conveniently ignore). Same were cited in submissions, same were opened in oral argument and same are expressly cited in the Draft Judgment (§92, §130(
  2. i)and (ii)). The reality for the Appellants (albeit one which they seem unwilling to accept - reflective of the unreality based nature of the evidence they sought to tender to the Court - a point which is also not addressed in their series of points raised in respect of the Draft Judgment), is that neither of the cases support their erroneous argument that the exempted development provisions under s.4
(1)(h) of the PDA apply. Appellants’ Point 5: ‘The Court errored [sic] in its interpretation of the Defences available under Section 4
(1)(h) as set out in Morris v Garvey the application of which defences apply to the facts of this case where it was a genuine belief based on a statutory exemption which related to no alteration of the character of the structure that would render the development inconsistent with the previous development or adjoining structures’. Council’s Response: It is not clear what the Appellants point here is by reference to the purpose of the Draft Judgment procedure. In any event the point, insofar as it refers to ‘defences’, is misconceived. Moreover, the Draft Judgment records that the Court considered Morris v Garvey [1983] IR 310 (§151 and §15B(xii)). The fact that the Applicants’ unreal contention that this unauthorised development occurred because of a ‘genuine mistake’ was correctly rejected does not disclose any issue with the Draft Judgment. The Court is not obliged to accept such misconceived contentions and the rejection of same is not a basis for seeking to revisit a Draft Judgment. Appellants’ Point 6: ‘It is also submitted that the Court errored [sic] in its interpretation of the defence of disproportionate hardship in terms of how it has been applied to the facts of this case’. Council’s Response: It is not clear what the Appellants point here is by reference to the purpose of the Draft Judgment procedure. This abstract complaint (not tethered to any specific part of the Draft Judgment) is baseless. The Court addressed the Appellants 11 arguments advanced in respect of the discretionary nature of the relief sought - the fact that same weren’t convincing is not a reason to revisit the Draft Judgment. Appellants’ Point 7: ‘Whether the finding of the court that this development commenced subsequent to the 1st October 1964 is consistent with the purpose of the Section 160
(6)(7 year rule) of the Planning & Development Act 2000, as amended’. Council’s Response: Again, it is not clear what the Appellants point here is by reference to the purpose of the Draft Judgment procedure. This abstract complaint is without merit and difficult to follow. In this regard, the development, works, commenced in August 2025 as the Draft Judgment records ( §113-§115). It is not suggested that this is incorrect - in fact, the agreed Statement of Case records the Appellants accepted this to be the case. Appellants’ Point 8: ‘Having regard to the defences raised, whether it is appropriate to make the cost orders contemplated in the draft judgment and in particular to the cost orders contemplated in the O’Neill proceedings in circumstances where those proceedings were commenced after the first return date of the SDCC proceedings’. Council’s Response: This is not a matter for the Council as it appears to be directed to the O’Neill proceedings. In any event, as to the Council’s case, the proposed costs orders are entirely appropriate. Appellants’ Point 9: ‘It is submitted that the Court errored [sic] in its interpretation of the reliefs sought by the Applicants and in particular those reliefs relating to the restoration of the lands to their condition immediately prior to the commenced of the development in August 2028’. Council’s Response: There was no error in the Draft Judgment in this respect ( §163 et seq), which notes the wide discretion available to the Court to make whatever order it deems appropriate - a position accepted by the Appellants (§165). Appellants’ Point 10: ‘The Court appears to make a finding that the original development consisted of mobile homes only. If that is indeed the finding of the Court, it is disputed by the Appellants’. Council’s Response: As outlined in the Council’s response to Point 1 above, the Court correctly understood the nature of the previous structures on the lands - as was evident from the exhibits opened to the Court (see, for example, Fifth Affidavit of Paul Byrne, SDCC, dated 251209) and, for example, by the recitation of the parties position as set out in the Statement of Case (mostly mobile homes). The Council’s exhibits set out the nature of the structures located on the lands previously - the Respondent did not establish in evidence of anything to the contrary, rather, it accepted the position but tried to argue the demolition and removal of same was exempted development. The Applicants’ Written Submissions accept that the previous structures on the lands comprise mobile-home type structures (§55): ‘ ...the character that has been replicated in terms of the appearance of the buildings with the height, the type of roof, the type of window detail, the type of materials used to be consistent with that of a mobile home type chalet...’ The Court was fully aware of the nature of the structures previously located on the lands with the central point being that once demolished and removed, they could not be the same structures (a point which the Appellants seem unwilling to accept). Indeed, this is expressly reflected in the proposed Order

§175

(iii), wherein the Court restrains the Appellants from ‘re-erecting caravans, mobile homes or other structures that have been removed ..’. Appellants’ Point 11: ‘The Court errored [sic] in its finding that both Affidavits of Ann Mulcrone were inadmissible on the basis that they should have been before the Court of first instance. The Appellants were given liberty to file an Affidavit in the Appeal. The Appellants submit that both affidavits should be admissible in the circumstances and on the basis of their relevance and

the very least should be heard in the question of inadmissibility’. Council’s Response: This really is not an appropriate point to raise in the Draft Judgment procedure. It is an entirely belated and inappropriate

tempt to address matters which the Appellants, for reasons only known to themselves, didn’t address

trial. The Council objected to the admissibility of these Affidavits in its Written Submissions and Statement of Case. The Appellants did not address this objection in any meaningful way - despite the opportunity to do so in Written Submissions, Statement of Case and oral submissions. It can’t seek to do so now that the case has concluded. Significantly, the point also doesn’t engage with the Draft Judgment and the reasons therein for determining the Affidavits to be inadmissible ( §107-§108). The Council do not consider that any of the points raised by the Appellants warrant further consideration by the Court and are wholly inappropriate in circumstances where the Appellants are or should be aware be aware that the Draft Judgment process is not for the purposes of re-arguing the matter which has already been heard.” 12

  1. The applicant in O’Neill replied as follows: “Thank you for the opportunity to reply to the respondent’s comments. We like to highlight some points relevant to item
  2. in the recent reply from the respondents wherein it is stated that: ‘Having regard to the defences raised, whether it is appropriate to make the cost orders contemplated in the draft judgment and in particular to the cost orders contemplated in the O’Neill proceedings in circumstances where those proceedings were commenced after the first return date of the SDCC proceedings.’ The Applicant’s position is as follows: - We wrote to the respondents with pre-litigation letters on the following dates 3rd October 2025, 7th October
  3. 10th October 2025, 21st October 2025 and the 23rd October 2025 and received no response despite threating to bring injunctive proceedings in the event of no reply. We also wrote to SDCC before our client issued their proceedings seeking details of enforcement action and we did not receive a substantive reply to our queries. - It was in these circumstances our client felt compelled to bring proceedings because he was directly affected by the development and lived right beside it and where the development was progressing apace without the benefit of any planning permission. - When the applicant applied for interim relief to the Circuit Court, the Court refused interim relief and made our application for interlocutory relief returnable for the same date as SDCC’s case and the proceedings then travelled together. - Judge O’ Connor in delivering judgment on 19th December expressly thanked the local residents for their assistance.”
  4. Any apparent clarity as to the joinder of issue was then fractured by the arrival

13.14 on 31 May 2026, the Sunday of a bank holiday weekend in the Whit vacation, of notifications of upload to ShareFile of the following two files: “260529 Appellants further response to draft judgment.msg Size 77.50 KB Date 05/31/2026 8:13:58 am User ... 260529 Appellants further response to draft judgment.msg Size 77.50 KB Date 05/31/2026 8:14:25 am User ... 84. The time of 8:13 am is predictably inaccurate, the emails by way of ShareFile notification arriving

13:14. The file name suggests that the responses were dated Friday 29 May 2026 – but were not uploaded on that date. The files arrived, needless to say, in a non-standard .msg format which I could not open (despite trying multiple apps for the purpose). All I could read was the header of one of them which purported to be an email dated 29 May 2026

17:00.39 – even then outside the time allowed albeit only just – almost as if one was making a point. The content was not readable. 85. For future reference it would be appreciated if parties could: (

  1. i)comply with timelines for submissions/ observations; (
  2. ii)upload documents as they are issued; (iii) limit themselves to readily accessible formats like .docx and .pdf – preferably .docx; and (
  3. iv)ensure their own internal systems are not set to generate inaccurate information such as regarding time/date. 86. The suspense was broken on Tuesday 2 June 2026, when I eventually received the content of the message. The content was: “Dear Registrar, We refer to the above matter and to the further request by the Court for further comments on the draft judgment until 5pm today. The following comments are additional to the comments submitted by the Appellants by email of 4pm on 27 May 2026 and should be read in conjunction with those comments. Please note that the comments are submitted in accordance with the requirements of HC137 in relation to draft judgments. The Appellants note that SDCC made no comments on the draft Judgment within the time prescribed for in the original timeline. The Appellants note that Mr O’Neill did make a comment in relation to the form of the order. In addition to the comment of the Appellants

bullet point 8 of their original commentary the Appellants do not accept that Mr O’Neill is entitled to seek to vary the terms and wording of the reliefs sought in his notice of motion. The O’Neill proceedings were brought

a point 13 after which the South Dublin County Council proceedings were before the Court and are in essence no more than a duplication of the SDCC proceedings. The O’Neill reliefs are encompassed in the SDCC proceedings, and it is respectfully submitted that there is no basis or jurisdiction to amend the reliefs now being sought. In addition, no application of that nature was made during the course of the hearing, and the Appellants would certainly need to be heard by Court if that application as to be considered or acceded to by the Court. Without prejudice to the forgoing the Appellants make the following additional comments arising from the judgment. 1. The Appellants assert that the Court errored [sic] in its interpretation of the established use of the development site

para 115 of the judgment. 2. The Appellants submit that the order

para 175(x)(a) are unworkable arbitrary and unfair having regard to the requirements of the Planning and Development Act 2000 as amended and the provisions of Section 4

(1)(h). 3. The Appellants submit that the order

para 175(x)(b) is in error and does not take account of the reliefs sought by both Respondents.

  1. The Appellants submit that it should and would have the opportunity to address the Court on any and all of the issues arising from the within comments and the original comments of Wednesday 27 May.”
  2. The statement that “Please note that the comments are submitted in accordance with the requirements of HC137 in relation to draft judgments” is unfortunately a complete misunderstanding and a non-reality-based statement from the respondents. The comments overall largely constitute an impermissible

tempt to reargue the substance, contrary to PD HC 137 and to any ordered and rational procedure. 88. The statement that “The Appellants note that SDCC made no comments on the draft Judgment within the time prescribed for in the original timeline” could give the unintendedly inaccurate impression that the council did not reply in time. The original letter stated “The deadline for comments is 16:00 on Wednesday 27 May 2026, and parties are required to positively respond one way or another by the deadline either with comments or confirmation that there are no comments.” The council’s email expressing no changes is timed

“Sent: 27 May 2026 10:07”.

  1. Insofar as the letter from the respondents requested to “address the court ... prior to the Court finalising its draft judgment”, the form of response envisaged by the draft judgment procedure is in writing and to a tight timetable, consistent with Practice Direction HC
  2. The concession of written corrections was made clear in the draft judgment when issued. Any jurisdiction, such as England & Wales, that envisages draft judgments operates on the basis of written comment, because it is obviously totally unworkable to have further oral hearings to reargue the substance of the case.
  3. That said, I have no particular objection to the respondents making submissions on the form of the order. But we need to be clear that such submissions will be within the contours of the judgment and not by way of rearguing the case, which would be totally improper and inappropriate.
  4. For the tiny minority interested in the mechanics of judgment production, maybe I can be forgiven for mentioning that an excessive and inappropriate

tempt to reargue the case on the basis of a draft judgment imposes considerable production pressures on the court. The present judgment involved a local record of 20 further internal drafts subsequent to the circulated draft in order to cope with the ebb and flow of that

tempt here (see previous relevant judgments for how numbers are calculated). This case is not a how-to guide for parties addressing draft judgments. Relief sought

  1. The reliefs sought by the council in the notice of motion before the Circuit Court are as follows: “
  2. An Order, pursuant to Section 160

(1)(a) of the Planning and Development Act 2000 (as amended), requiring the Defendants, their respective servants, agents, licensees or any persons acting in connection with them or on their instruction, to cease and/or refrain from carrying out unauthorised development (as more particularly described in the Affidavit of Paul Byrne),

the lands located Chianti Park, Mount Seskin Road, Raheen, Brittas, Co Dublin (‘the Lands’) (as more particularly described in the Affidavit of Paul Byrne), comprising the following: (

  1. i)Site clearance works and the demolition and removal of multiple chalets and mobilehome structures from the Lands. (
  2. ii)The laying of serviced concrete platforms/foundations – and all works associated with servicing same, including installation of electrical cabling and waste/water pipework. (iii) The development of multiple new accommodation/chalet structures on the Lands. 2. An Order, pursuant to Section 160

(1)(b) of the Planning and Development Act 2000 (as amended), requiring the Defendants, their respective servants, agents, licensees or any persons acting in connection with them or on their instruction, to remove the unauthorised development referred to

paragraph 1 above and to restore the Lands to the condition that 14 such lands were in prior to the commencement of the unauthorised development referred to

paragraph 1 above. 3. Interim and/or interlocutory relief, pursuant to Section 160

(3)(a) of the Planning and Development Act 2000 (as amended), as may be necessary.
  1. Such further or other order as this Honourable Court shall deem fit.
  2. The costs of these proceedings.”
  3. In the O’Neill case the reliefs were as follows (relief 3 having been amended by consent in the Circuit Court prior to the hearing per underlined wording): “
  4. An Order pursuant to section 160
(1)(a) of the Planning and Development Act 2000 (as amended), restraining the Respondent, its servants, agents, or licensees, or any person acting in concert with them and any person having knowledge of such Order, from carrying out or continuing to carry out unauthorised development and/or unauthorised use

the property (the ‘Property’) known as Chianti Park, Mount Seskin, Brittas, County Dublin and identified in the Schedule to the Notice of Motion; 2. An Order pursuant to section 160

(1)(a) of the Planning and Development Act 2000 (as amended), enjoining the Respondent, its servants, agents, or licensees, or any person acting in concert with them and any person having knowledge of such Order, to cease and desist from carrying out any unauthorised development on and/or unauthorised use of the Property; 3. An Order pursuant to section 160
(1)(
  1. b)of the Planning and Development Act 2000 (as amended), directing the Respondent, its servants, agents, or licensees, or any person acting in concert with them and any person having knowledge of such Order, to restore the Property to its condition before its/the unauthorised development; 4. Interlocutory Orders in terms of the above paragraphs, or such Orders as this Honourable Court shall deem appropriate pending the hearing of the within application; 5. An Order granting the Applicant and its experts permission to enter onto the Property and inspect, survey, observe, photograph, and investigate the same, prior to the determination of these proceedings; 6. A determination pursuant to section 7 of the Environment (Miscellaneous Provisions) Act 2011 that section 3 of the said Act applies to these proceedings; 7. Such further or other Order, including declaratory relief, as this Honourable Court shall deem appropriate; 8. An Order providing for the costs of this application; 9. Liberty to file further affidavits, 10. Such further or other Order as this Honourable Court deems fit.” Order of the Circuit Court 94. While ideally in a circuit appeal, the High Court would not be told of the order, that wasn’t an option here not least because of the extensive publicity given to the matter. The orders were identical apart from the title and apart from the fact that the SDCC order covered two counsel. The O’Neill order provides as follows: “DUBLIN CIRCUIT COUNTY OF THE CITY OF DUBLIN BEFORE JUDGE O’CONNOR THE 19th DAY OF December 2025 IN THE MATTER OF THE PLANNING AND DEVELOPMENT ACT 2000 (AS AMENDED) NOTICE OF MOTION FOR RELIEF UNDER SECTION 160 OF THE PLANNING AND DEVELOPMENT ACT 2000 (AS AMENDED) BETWEEN John O’Neill PLAINTIFF AND Branach Development Limited and Mullnassa Limited DEFENDANTS The application coming before the Court this day on Motion on behalf of the Plaintiffs for reliefs pursuant to Section 160(l)(
  2. a)and (
  3. b)of the Planning and Development Act 2000 (as amended). WHEREUPON and on hearing Counsel for the Plaintiffs and Counsel for the Defendants. AND THE COURT having adjourned the matter for Judgement to this day THE COURT DOTH ORDER 1. An Order, pursuant to Section 160(l)(
  4. a)of the Planning and Development Act 2000 (as amended), requiring the Defendants, their respective servants, agents, licensees or any persons acting in connection with them or on their instruction, to cease and/or refrain from carrying out unauthorised development (as more particularly described in the Affidavit of 15 Paul Byrne),

the lands located

Chianti Park, Mount Seskin Road, Raheen; Brittas, Co. Dublin (‘the Lands’) (as more particularly described in the Affidavit of Paul Byrne), comprising the following : (

  1. i)Site clearance works and the demolition and removal of multiple chalets and mobilehome structures from the Lands; (
  2. ii)The laying of serviced concrete platforms/foundations - and all works associated with servicing same, including installation of electrical cabling and waste/water pipework; (iii) The development of multiple new accommodation/chalet structures on the Lands. 2. An Order, pursuant to Section 160

(1)(b) of the Planning and Development Act 2000 (as amended), requiring the Defendants, their respective servants, agents, licensees or any persons acting in connection with them or on their instruction, to remove the unauthorised development referred to

paragraph 1 above within 4 months and to restore the Lands to the condition that such lands were in prior to the commencement of the unauthorised development referred to

paragraph 1 above within 8 months. THE COURT DOTH ORDER that the Plaintiff do recover from the Defendants costs of the proceedings, to include a Certificate for Junior Counsel, such costs to be taxed in default of agreement. THE COURT DOTH MAKE AN ORDER granting liberty to the Defendants to take up the DAR transcript of today’s Judgement, on the undertaking that they pay for the transcript and furnish a copy of the transcript to the Plaintiff’s Solicitor. BY THE COURT … (SEAL) NOMINATED SIGNATORY BY THE COMBINED OFFICE MANAGER Order settled by … Draft Order settled on 22/12/2025” 95. The reference to taxation of costs is the procedure in the Circuit Court. Adjudication applies to the High Court and upwards. Section 160 96. Section 160 of the 2000 Act provides (emphasis added): “160.—

(1)Where an unauthorised development has been, is being or is likely to be carried out or continued, the High Court or the Circuit Court may, on the application of a planning authority or any other person, whether or not the person has an interest in the land, by order require any person to do or not to do, or to cease to do, as the case may be, anything that the Court considers necessary and specifies in the order to ensure, as appropriate, the following: (
  1. a)that the unauthorised development is not carried out or continued; (
  2. b)in so far as is practicable, that any land is restored to its condition prior to the commencement of any unauthorised development; (
  3. c)that any development is carried out in conformity with— (
  4. i)in the case of a permission granted under this Act, the permission pertaining to that development or any condition to which the permission is subject, or (
  5. ii)in the case of a certificate issued by the Dublin Docklands Development Authority under section 25
(7)(a)(ii) of the Dublin Docklands Development Authority Act 1997 or by the Custom House Docks Development Authority under section 12
(6)(b) of the Urban Renewal Act 1986, the planning scheme made under those Acts to which the certificate relates and any conditions to which the certificate is subject.
(2)In making an order under subsection
(1), where appropriate, the Court may order the carrying out of any works, including the restoration, reconstruction, removal, demolition or alteration of any structure or other feature.
(3)(
  1. a)An application to the High Court or the Circuit Court for an order under this section shall be by motion and the Court when considering the matter may make such interim or interlocutory order (if any) as it considers appropriate. (
  2. b)Subject to section 161, the order by which an application under this section is determined may contain such terms and conditions (if any) as to the payment of costs as the Court considers appropriate.
(4)(
  1. a)Rules of court may provide for an order under this section to be made against a person whose identity is unknown. (
  2. b)Any relevant rules of Court made in respect of section 27 (inserted by section 19 of the Act of 1992) of the Act of 1976 shall apply to this section and shall be construed to that effect.
(5)(
  1. a)An application under this section to the Circuit Court shall be made to the judge of the Circuit Court for the circuit in which the land which is the subject of the application is situated. 16 (
  2. b)The Circuit Court shall have jurisdiction to hear and determine an application under this section where the market value of the land which is the subject of the application does not exceed €3,000,000. (
  3. c)The Circuit Court may, for the purposes of paragraph (b), in relation to land that has not been given a market value or is the subject with other land of a market value, determine that its market value would exceed, or would not exceed, €3,000,000. (
  4. d)Where the market value of any land which is the subject of an application under this section exceeds €3,000,000, the Circuit Court shall, if an application is made to it in that behalf by any person having an interest in the proceedings, transfer the proceedings to the High Court, but any order made or act done in the course of such proceedings before the transfer shall be valid unless discharged or varied by the High Court by order. (
  5. e)In this subsection ‘market value’ means, in relation to land, the price that would have been obtained in respect of the unencumbranced fee simple were the land to have been sold on the open market, in the year immediately preceding the bringing of the proceedings concerned, in such manner and subject to such conditions as might reasonably be calculated to have resulted in the vendor obtaining the best price for the land. (5A) (
  6. a)An application under this section to the Circuit Court shall, in respect of development situated wholly or partly in the nearshore area of a coastal planning authority, be made to the judge of the Circuit Court for the circuit in which the functional area (other than the nearshore area) of that coastal planning authority is situated. (
  7. b)The Circuit Court shall have jurisdiction to hear and determine an application under this section in relation to a development referred to in paragraph (
  8. a)where the aggregate amount of the levy or levies payable under Chapter 7 of Part 4 of the Maritime Area Planning Act 2021 in respect of the maritime area consent granted to the person who carried out the development does not exceed €500,000. (5B) (
  9. a)An application under this section, in respect of development situated wholly or partly in the nearshore area of a coastal planning authority, shall be made to the High Court if that development was carried out by or on behalf of a person who

the time of the carrying out of the development was not the holder of a maritime area consent granted for the occupation of a maritime site for the purposes of the proposed development. (b) An application under this section, in respect of development situated wholly in the outer maritime area, shall be made to the High Court.

(6)(
  1. a)An application to the High Court or Circuit Court for an order under this section shall not be made— (
  2. i)in respect of a development where no permission has been granted, after the expiration of a period of 7 years from the date of the commencement of the development, (
  3. ii)in respect of a development for which permission has been granted under Part III or section 293, after the expiration of a period of 7 years beginning on the expiration, as respects the permission authorising the development, of the appropriate period (within the meaning of section 40) or, as the case may be, of the appropriate period as extended under section 42, or (iii) in respect of a development in respect of which a certificate has been issued by the Dublin Docklands Development Authority under section 25
(7)(a)(ii) of the Dublin Docklands Development Authority Act 1997 or by the Custom House Docks Development Authority under section 12
(6)(
  1. b)of the Urban Renewal Act 1986, after the expiration of a period of 7 years beginning on the date the certificate ceases to have effect in accordance with Part 4 of the Dublin Docklands Development Authority (Dissolution) Act 2015. (
  2. aa)Notwithstanding paragraph (
  3. a)an application to the High Court or Circuit Court for an order under this section may be made

any time in respect of unauthorised quarry development or unauthorised peat extraction development in the following circumstances: (

  1. i)where no permission for the development has been granted under Part III and the development commenced not more than 7 years prior to the date on which this paragraph comes into operation; (
  2. ii)where permission for the development has been granted under Part III and, as respects the permission— (I) the appropriate period (within the meaning of section 40), or (II) the appropriate period as extended under section 42 or 42A, expired not more than 7 years prior to the date on which this paragraph comes into operation. 17 (
  3. ab)Notwithstanding paragraph (
  4. a)or (aa), an application to the High Court or Circuit Court may be made

any time for an order under this section to cease unauthorised quarry development or unauthorised peat extraction development. (b) Notwithstanding paragraph (a), an application for an order under this section may be made

any time in respect of any condition to which the development is subject concerning the ongoing use of the land.

(7)Where an order has been sought under this section, any other enforcement action under this Part may be commenced or continued.” Procedure on circuit appeals
  1. An appeal from the Circuit Court to the High Court is by way of rehearing. Thus even if it is the respondent is appealing, the applicant goes first. That is an instance of the general principle that the party bearing the onus of proof goes first (which is why, for example, the respondent in an Article 40.4 application goes first – the order is determined by the burden of proof and not by the title “applicant”). Thus in a circuit appeal, the concept of the applicant going first would not apply if the only issue was one on which the respondent carried such a burden. The respondents carried the burden to show this was exempted development, which was the main issue, but in fact the respondents didn’t avail of any rights to open the appeal that arose from that but (rightly or wrongly) asked for the applicants to go first, a request which I humoured in the circumstances.
  2. The procedure for an appeal depends on whether oral evidence was heard and also on what circuit the matter originated in. Case heard on oral evidence from provincial circuits are heard by the High Court on Circuit. Cases originating in Dublin or heard without oral evidence elsewhere generally go to the Non-Jury List, except insofar as they relate to planning and environment matters which go to the Planning & Environment Court (see PD HC 137).
  3. In terms of evidence in such a rehearing, s. 37 of the Courts of Justice Act 1936, as amended, provides: “
(1)An appeal shall lie to the High Court sitting in Dublin from every judgment given or order made (other than judgments and orders in respect of which it is declared by this Part of this Act that no appeal shall lie therefrom) by the Circuit Court in any civil action or matter

the hearing or for the determination of which no oral evidence was given. (1A) Notwithstanding subsection

(1), an appeal shall lie to the High Court sitting in Dublin from every judgment given or order or decision made (other than a decision to which section 169
(4)of the Personal Insolvency Act 2012 applies) by the Circuit Court in the performance of any function or exercise of any power or jurisdiction conferred on that court by that Act, whether or not oral evidence was given

the hearing or for the determination of the proceedings or matter concerned.

(2)Every appeal under this section to the High Court shall be heard and determined by one judge of the High Court sitting in Dublin and shall be so heard by way of rehearing of the action or matter in which the judgment or order the subject of such appeal was given or made, but no evidence which was not given and received in the Circuit Court shall be given or received on the hearing of such appeal without the special leave of the judge hearing such appeal.”
  1. Order 61 RSC includes inter alia the following (emphasis added): “
  2. An appeal shall not operate as a stay of proceedings upon the judgment or Order appealed from unless the Circuit Judge, or, upon appeal, the High Court sitting in Dublin shall so order and then only upon such terms (if any) as the Circuit Judge or the High Court sitting in Dublin (as the case may be) may fix. Such appeal shall be by notice of motion served on all parties affected by the application and lodged in the Central Office within four days of the application to the Circuit Judge. …
  3. Where any party desires to submit fresh evidence upon the hearing of an appeal in any action or matter

the hearing or for the determination of which no oral evidence was given, he shall serve and lodge an affidavit setting out the nature of the evidence and the reasons why it was not submitted to the Circuit Court. Any party on whom such affidavit has been served shall be entitled to serve and lodge an answering affidavit or to apply to the Court on the hearing of the appeal for leave to submit such evidence, oral or otherwise, as may be necessary for the purpose of answering such fresh evidence, provided, however, that the Court may

any time admit fresh evidence, oral or otherwise on such terms as the Court shall think fit, and may order the

tendance for cross-examination of the deponent in any affidavit used in the Circuit Court or the High Court. … 11

(1)Every judgement or order of the High Court on Circuit shall be drawn up and signed by the County Registrar, and every judgement or order of the High Court sitting in Dublin shall be drawn up and signed by the Registrar of such Court, who shall transmit a copy 18 thereof to the County Registrar of the appropriate county. Every judgement or order of the Court shall state whether it is made with or without costs and the sum (if any) payable for costs, including witnesses’ expenses, shall be inserted therein, except in such cases as the Court may refer such costs and expenses for taxation.
(2)A copy of every judgement or order of the High Court on Circuit in a Circuit appeal from or against the making of an order transferring any civil action to the Court from the Circuit Court or an order sending forward any civil action or appeal to the Court from the Circuit Court shall be remitted to the proper officer of the Central Office forthwith on its being signed.
  1. The costs of appeals, when referred for taxation, shall be taxed by the appropriate County Registrar (who shall for this purpose have all the powers of a Legal Costs Adjudicator). Such costs shall, subject to any special direction by the Court, be taxed on the scale applicable to an action or matter commenced or heard in the Circuit Court, with the addition of necessary outlay and the items set out in Part III of the scales of costs in Appendix W. Any application for the review of a taxation effected under this rule shall be by notice of motion to the High Court sitting in Dublin served on all parties affected by the application and lodged in the Central Office within ten days from the date of the certificate of taxation. The notice of motion shall specify the matters or items or parts thereof objected to and the grounds and reasons for such objection. A copy of the notice of motion shall be transmitted forthwith from the Central Office to the County Registrar for his report or observation thereon. In the taxation of costs under this rule, the County Registrar shall, in addition to the principles specified in Schedule 1 to the Legal Services Regulation Act 2015, have regard to the costs allowed or allowable in respect of the hearing of the case in the Circuit Court. …
  2. Every judgment or order of the High Court on Circuit and of the High Court sitting in Dublin may (unless the Court shall otherwise direct) be enforced by execution order issued by the Circuit Court in accordance with the Rules of the Circuit Court for the time being in force as if it were a judgment or order of the Circuit Court.” Onus of proof
  3. The onus is on a defendant to establish that development is exempted development: South Dublin County Council v. Fallowvale Limited [2005] IEHC 408 (Unreported, High Court, McKechnie J., 28 April 2005); Doorly v. Corrigan [2022] IECA 6 (Unreported, Court of Appeal, 21 January 2022) (Ní Raifeartaigh and Pilkington JJ. concurring)

§121. 102.

Any such defence must be capable of being distilled from the affidavit evidence before the court: Diamrem Ltd. v. Cliffs of Moher Centre Ltd [2018] IEHC 654 (Unreported, High Court, Faherty J., 20 November 2018) (§157-§160), a decision upheld by the Court of Appeal in Diamrem Ltd. v. Cliffs of Moher Centre Ltd [2021] IECA 291 (Unreported, Court of Appeal, Woulfe J., 5 November 2021).

  1. In that regard, the court is not obliged to accept vague and unsubstantiated averments: Tesco Ireland Limited v. Stateline Transport Limited [2024] IECA 46 (Unreported, Court of Appeal, Butler J., 23 February 2024) (Costello and Noonan JJ. concurring) (§63).
  2. While the appellants relied on Michael Cronin (Readymix) v. An Bord Pleanála [2017] IESC 36, [2017] 2 I.R. 658 (O’Malley J.; MacMenamin and Laffoy JJ. concurring)

39, referring to the fact that a defendant only needs to raise a reasonable doubt, that is self-evidently a statement in the criminal context. It has no relevance to civil enforcement.

  1. Given the onus of proof, the lack of cross examination is fatal to the respondents. Where there is a conflict of admissible evidence, in the absence of cross-examination such a conflict must generally be resolved against the party carrying the onus of proof: RAS Medical Ltd v. Royal College of Surgeons in Ireland [2019] IESC 4, [2019] 1 I.R. 63, [2019] 2 I.L.R.M. 273 (Clarke C.J.) (O’Donnell, MacMenamin, Dunne and Finlay Geoghegan JJ. concurring).
  2. Two further matters regarding the affidavit evidence for the respondents unfortunately occasion some concerns.
  3. The more specific one is the misplaced use on affidavit of the title “Architect” by Mr Adrian Donoghue who is not a registered architect. He is an “architectural graduate”, and my understanding of the practical effect of s. 18 of the Building Control Act 2007 which criminalises the use of the term “architect” by a non-registered person in specified circumstances.
  4. His latest affidavit begins: “
  5. I say that I am an qualified architect having graduated in 2005 from Edinburgh University with a BA Architecture. I say that I have been practicing in Ireland as an Architect and I am the principal of Adrain [sic] Donoghue Design Studio. I say that Adrian Donoghue Design Studio have been retained as a consulting architect by the First and Second Named Defendants in respect of the development known as Chianti Park and Hillbrook Lawns located 19

located

Raheen, Brittas, Co. Dublin and in that regard and I am duly authorised to make this affidavit for and on behalf of the First and Second Named Defendants from facts within my own knowledge, save where otherwise appears whereso appearing I believe same to be true.”

  1. He is referred to as an “Architect” throughout the respondents’ legal submissions.
  2. In this affidavit he purports to give a “professional opinion”, e.g. para.
  3. Counsel’s response was that the word “architect” was used in the sense of graduate. That concept in other contexts can be non-problematic, for example someone with a degree in law could, depending on the context, call themselves a lawyer even if not practising or qualified to practice. But the whole point of a protected title is that once protected, people are not entitled to use that title in their own sense. The protection requires people to use the term only in the sense defined by law. That’s the point that the respondents are missing.
  4. The dismissive response to this perfectly legitimate concern was unfortunately misplaced. I did give an opportunity for a further affidavit on this issue but have not been notified of that having been taken up. On the contrary the respondents doubled down on their position in their further correspondence to the court so I will be open to any proposals from the applicants as to how best to address this problem.
  5. The more general point is that certain of the matters sworn to on behalf of the respondent include averments that fly in the face of reality and that no reasonable person could have sworn to. A prime example is para. 13 of Mr Donoghue’s second affidavit (emphasis added): “
  6. I say that I was careful in advising on the design to ensure that the said design was such as to create no material change in the appearance. I say that I have prepared a series of drawings showing the appearance of residential units as they were before works were carried out and the design as they appear when they are complete and I beg to refer to a copy of said drawings located

TAB 4 of the Booklet of Exhibits.”

  1. As outlined above, this is a non-reality-based averment. The necessary implication that the new design did not in fact involve a material change to the appearance of the structures is manifestly false and untenable and lacks any stateable basis whatsoever.
  2. The council put Mr Donoghue fully on notice of the complete unreality of this via their affidavits – any reply was little more than a repetition and certainly not an answer. I am not offering a view on deliberateness or culpability, merely on the total objective unreasonableness of such an averment which does nothing for the weight to be

tached to his evidence generally, even assuming that it otherwise warranted weight given that the burden to show exempted development lies on the developers and must be resolved against them in the absence of cross-examination. 116. The legal context is that while conflict between equally inherently credible averments, with no cross-examination, is generally resolved against the party carrying the onus of proof, a court is not always obliged to regard all averments as being equally credible, or to disregard internal or evident problems with them (see by analogy the manner in which the Supreme Court considered it was entitled to prefer an affidavit over even oral evidence in Koulibaly v. Minister for Justice, Equality and Law Reform [2004] IESC 50, [2004] 7 JIC 2906 (Unreported, Supreme Court, Denham J. (Geoghegan and McCracken JJ. concurring), 29 July 2004)). Among the matters to which regard might be had would be included the failure to explain patently relevant questions that are clearly within that party’s responsibility (Doorly v. Corrigan [2022] IECA 6 (Unreported, Court of Appeal, 21 January 2022)

para. 137). This specific and common sense power of the court to evaluate inherent defects in evidence remains notwithstanding caselaw on cross-examination such as RAS Medical Ltd v. Royal College of Surgeons in Ireland [2019] IESC 4, [2019] 1 I.R. 63, [2019] 2 I.L.R.M. 273 (Clarke C.J.) (O’Donnell, MacMenamin, Dunne and Finlay Geoghegan JJ. concurring) or Re Bayview Hotel (Waterville) Limited [2022] IEHC 516 (Unreported, High Court, Butler J., 8 September 2022). This is consistent by analogy with the judgment of Hardiman J. (Hanna and Feeney JJ. concurring) in DPP v. Barnes [2006] IECCA 165, [2007] 3 I.R. 130, [2007] 1 I.L.R.M. 350

para. 95 – the court as finder of fact is “not ... constrained” to accept “the only account available” even if that account is provided by oral evidence. The issues here 117. As to the necessary proofs there is no issue about the following: (

  1. i)there was development (not an issue save in relation to tree cutting); (
  2. ii)there is no planning permission; and (iii) the jurisdiction of the Circuit Court by reference to rateable valuation – this had been a concern

an earlier stage but the respondents confirmed they are not making an issue of it now. 118. Thus the issues are the following: (

  1. i)an issue about admissibility of affidavits; (
  2. ii)whether this was pre-1964 development; (iii) the seven-year rule; 20 (
  3. iv)whether tree cutting was development; (
  4. v)whether this is exempted development; (
  5. vi)in the event of breach, the question of discretion; and (vii) in the event of an order, the form of such order. Issue 1 – admissibility of affidavits 119. The appellants have sought to introduce new evidence for the purpose of this appeal, including from a planner, Ms Mulcrone. This is not admissible because such evidence was not adduced before the Circuit Court (when it could have been) and no explanation has been provided for the failure to do so, and no special leave was sought from or granted by the High Court. Thus the affidavit is out by reason of a failure to engage with O. 61 r. 8 RSC and s. 37 of the Courts of Justice Act 1936 (see e.g.: Murphy v. Minister for Defence 1991 WJSC-SC 981, [1991] 2 I.R. 161; Emerald Meats v. Minister for Agriculture [2012] IESC 48 (Unreported, Supreme Court, 30 July 2012) per O’Donnell J. (Hardiman and McKechnie JJ. concurring)

§36; Student Transport Scheme Limited v.

Minister for Education and Skills [2015] IECA 303 (Unreported, Court of Appeal, Hogan J., 18 December 2015) (Ryan P. and Peart J. concurring) (§10); Wicklow County Council v. Beattie [2018] IEHC 282 (Unreported, High Court, Barrett J., 17 May 2018); Kerry County Council v. McElligott [2021] IEHC 542 (Unreported, High Court, Hyland J., 30 July 2021) (§33); Lyons v. McDonagh [2024] IEHC 471 (Unreported, High Court, Simons J., 31 July 2024) (§14), wherein the court noted that “the respondents should have applied to the judge for special leave to file an affidavit…required under [s. 37]…and Order 61…”).

  1. The respondents seem to be labouring under the misunderstanding that obtaining de bene esse liberty to file an affidavit constitutes the sort of special leave envisaged by s. 37 and O. 61 RSC. That is not the case. A de bene esse permission is subject to objection – and there was an objection. That should have triggered the formal application for special leave. No such application was made.
  2. Even if I am wrong about the foregoing, no weight should be

tached to the new evidence as in the absence of cross-examination the respondents have not discharged the onus of proof on the issue of exempted development. Furthermore Ms Mulcrone’s affidavit contradicts other affidavits of the respondents regarding the date of commencement of the caravan/ mobile home park. 122. The respondents also misleadingly

tempted to cry foul in the draft judgment process by demanding a “right to be heard” on the admissibility of the affidavits. But where have they been all this time? The council maintained the objection from the outset of such affidavits, and put it in lights in submissions. The respondents could have said anything they wanted

the hearing. The respondents now turn around and claim to be victims denied a right to be heard - but they were heard. A right to a hearing does not involve a right to be spoon-fed: Y.Y. v. Minister for Justice and Equality (No. 1) [2017] IEHC 176 (Unreported, High Court, 13 March 2017), para. 95 (this point wasn’t affected by the judgment in Y.Y. v. Minister for Justice and Equality [2017] IESC 61, [2018] 1 I.L.R.M. 109 (O’Donnell J.)); Friends of Killymooney Lough v. An Coimisiún Pleanála [2025] IEHC 407 (Unreported, High Court, 16 July 2025).

  1. The council’s written legal submissions contain the following: “
  2. Noting that the burden is on the Appellants to establish that the said works comprise exempted development, and whilst it is submitted that the evidence of the Council (including photographs) clearly demonstrates that the Appellants’ position is untenable, the following comments can be made about the evidence adduced: The Appellants have sought to introduce new evidence for the purpose of this appeal, including from a planner – Ms Mulcrone. The Council objects to the admissibility of this Affidavit (and indeed the further Affidavit from Mr McDermott) in circumstances where such evidence was not adduced before the Circuit Court (when it could have been) and no explanation has been provided for the failure to adduce same. In this regard, Order 61 Rule 8 of the Rules of the Superior Courts provides: ‘Where any party desires to submit fresh evidence upon the hearing of an appeal in any action or matter

the hearing or for the determination of which no oral evidence was given, he shall serve and lodge an affidavit setting out the nature of the evidence and the reasons why it was not submitted to the Circuit Court. Any party on whom such affidavit has been served shall be entitled to serve and lodge an answering affidavit or to apply to the Court on the hearing of the appeal for leave to submit such evidence, oral or otherwise, as may be necessary for the purpose of answering such fresh evidence, provided, however, that the Court may

any time admit fresh evidence, oral or otherwise on such terms as the Court shall think fit, and may order the

tendance for cross-examination of the deponent in any affidavit used in the Circuit Court or the High Court.’ Moreover, the Appellants have not complied with s.37 of the Courts of Justice Act 1936, as amended, insofar as special leave was not sought from this Honourable Court. Section 37 provides: 21 ‘

(1)An appeal shall lie to the High Court sitting in Dublin from every judgment given or order made (other than judgments and orders in respect of which it is declared by this Part of this Act that no appeal shall lie therefrom) by the Circuit Court in any civil action or matter

the hearing or for the determination of which no oral evidence was given. (1A) Notwithstanding subsection

(1), an appeal shall lie to the High Court sitting in Dublin from every judgment given or order or decision made (other than a decision to which section 169
(4)of the Personal Insolvency Act 2012 applies) by the Circuit Court in the performance of any function or exercise of any power or jurisdiction conferred on that court by that Act, whether or not oral evidence was given

the hearing or for the determination of the proceedings or matter concerned.

(2)Every appeal under this section to the High Court shall be heard and determined by one judge of the High Court sitting in Dublin and shall be so heard by way of rehearing of the action or matter in which the judgment or order the subject of such appeal was given or made, but no evidence which was not given and received in the Circuit Court shall be given or received on the hearing of such appeal without the special leave of the judge hearing such appeal. …’ Order 61 Rule 8 of the RSC and s.37 have been addressed in a number of s.160 appeals – including Kerry County Council v McElligott [2021] IEHC 542 (§33); Lyons v McDonagh [2024] IEHC 471 (§14), wherein the Court noted that ‘the respondents should have applied to the judge for special leave to file an affidavit…required under [s.37]…and Order 61…’; and Wicklow County Council v Beattie [2018] IEHC 282. No explanation has been provided by the Appellants for the failure to adduce this evidence before the Circuit Court – which could have been so adduced with reasonable diligence. Same should not be admitted. See also Murphy v Minister for Defence [1991] 2 I.R. 161; Student Transport Scheme Limited v. Minister for Education and Skills [2015] IECA 303 (§10); and Emerald Meats v Minister for Agriculture [2012] IESC 48, wherein O’Donnell J observed (§36): ‘The rules on the admission of fresh evidence on an appeal are quite strict. This is as it should be. There are very few cases in which the losing side does not regret that different witnesses were called, evidence given or points made either in cross-examination or in submission. But a trial is not a laboratory experiment where one element can be substituted and all other elements maintained and a different outcome obtained. It is important that parties are aware of the finality of litigation, and bring forward their best case for adjudication’. Without prejudice to the foregoing, the substance of the Affidavit from Ms Mulcrone does not add anything to the case. It comprises a reiteration of the Appellants’ flawed submissions which were advanced before the Circuit Court relating to s.4
(1)(h) of the PDA and makes a number of unsubstantiated averments which are in fact inconsistent with the Appellants’ other Affidavits – including in respect of pre-1964 use (the Appellants’ evidence before the Circuit Court was that the use of the Lands for residential purposes has occurred ‘since approximately 1968…’). Mr Donoghue purports to be an architect, but does not appear to be and does not aver that he is registered with the RIAI. Section 18 of the Building Control Act 2007, as amended, contains a prohibition against using the title/term architect unless registered. The Appellants have not adduced any evidence and do not address their claim of exempted development by reference to the actual structures previously located on the Lands (an approach repeated by Ms Mulcrone). Rather, they vaguely refer to ‘residential dwellings’ being located on the Lands, but

no point do they actually acknowledge that the previous structures mostly comprised mobile homes (although, it appears that Ms Mulcrone accepts that this was the case insofar as she refers to previous/historic enforcement action). Noting that the burden of proving the exemption rests on them, the failure of the Appellants to engage in this basic exercise is fatal to their misconceived

tempt to rely on same. For example,

no point do the Appellants acknowledge the previous mobile home structures located on the Lands and then

tempt to explain how the new structures comprise improvements/repair to same. The reason for this failure is obvious – they simply cannot make such a claim as the new structures are manifestly not mobile homes, but rather are completely different, new larger structures. The Appellants have adduced no evidence to establish existing foundations on the Lands – noting that the photographs depict mobile homes on blocks. Moreover, even if foundations did previously exist on the Lands, the Council’s photographs depict the development of new larger and materially different foundations with new services to same. Again, none of the Appellants’ deponents

tempt to engage with this evidence. Noting the 22 restrictive interpretation to s.4

(1)(h) of the PDA, it is simply not credible to argue, as the Appellants enthusiastically

tempt to, that these comprise repairs to the alleged existing foundations. The evidence demonstrates that the new structures are considerably larger and different from those previously located on the Lands – which is consistent with the need for new larger foundations. The Appellants do not address the fact that there were clearly parts of the site where no structures were located

the time they commenced the unauthorised development – it is thus simply not possible to suggest that the unauthorised works comprise improvement works to a non-existent structure. The Appellants have not adduced any evidence from anyone who actually carried out the unauthorised works – this includes the Third Named Appellant. The contentions regarding what was on the Lands before the works started and what is now there are lacking any evidential substance. Many of the averments made as to the condition of the Lands and the structures thereon before the commencement of the unauthorised development ignore the evidence adduced by the Council of the nature of the previous structures on the Lands – for example, the Appellants completely ignore (and do not dispute) the evidence of mobile homes being previously located on the Lands. 46. The Appellants have not remotely discharged the onus of proof which they bear that the unauthorised works are repair works to existing structures for the purposes of s.4

(1)(h) of the PDA – which they clearly are not.” 124. It was up to the respondents to reply to that

the hearing if they wanted to – they did not rebut that in any meaningful way. The claim of a “right to be heard” is in essence a claim to a “right to reargue the case having lost”. No rational, self-respecting, serious, developed legal system could operate on that basis. The council’s reply, which I endorse, is pretty devastating: “It is an entirely belated and inappropriate

tempt to address matters which the Appellants, for reasons only known to themselves, didn’t address

trial. The Council objected to the admissibility of these Affidavits in its Written Submissions and Statement of Case. The Appellants did not address this objection in any meaningful way - despite the opportunity to do so in Written Submissions, Statement of Case and oral submissions. It can’t seek to do so now that the case has concluded. Significantly, the point also doesn’t engage with the Draft Judgment and the reasons therein for determining the Affidavits to be inadmissible (§107-§108).” Issue 2 – whether this was pre-1964 development 125. The respondents accept that their averments (Mr McDermott first affidavit para. 6, Mr Donoghue

para. 6) that a development had taken place “since approximately 1968” is mere assertion, and they also accept that they have no actual evidence that there was a development of any relevant kind in place here pre-1964. 126. So it is not

all clear to me why they made this even formally an issue in the case. Doing so is, unfortunately, wholly without merit and bound to fail. This is a frivolous point, to use a somewhat superseded but unfortunately appropriate term.

  1. Even if counterfactually there had been a development pre-1964, the various changes and intensifications since then and in particular the completely new works since August 2025 mean that we are dealing now with a new development which cannot avail of the pre-1964 defence. Issue 3 – the seven-year rule
  2. As noted in Rutledge v. Fingal County Council [2026] IEHC 223 (Unreported, High Court, 17 April 2026)

97 in relation to uses, but analogous principles are relevant to works: (

  1. i)“abandonment and resumption can defeat any seven year defence: see e.g. South Dublin County Council v. Balfe (Unreported, High Court, Costello P., 3 November 1995); Kildare County Council v. Goode & Ors. (Unreported, High Court, Morris J., 13 June 1997); Sligo County Council v. Martin [2007] IEHC 178 (Unreported, High Court, O’Neill J., 24 May 2007); Pierson v. Keegan Quarries Ltd [2010] IEHC 404 (Unreported, High Court, Irvine J., 7 October 2010); Wicklow County Council v. Lee [2019] IEHC 19 (Unreported, High Court, Noonan J., 15 January 2019); (
  2. ii)permission for an inconsistent use can be evidence of abandonment thus necessitating permission for a resumption of the previous use: Clonres v. An Bord Pleanála [2021] IEHC 303 (Unreported, High Court, 7 May 2021), §37; Leitrim County Council v. Dromaprop Ltd [2024] IEHC 233 (Unreported, High Court, 29 April 2024), §33-35; Murphy v. An Bord Pleanála [2024] IEHC 186 (Unreported, High Court, Farrell J., 30 August 2024), §42; Ó Murthuile v. An Bord Pleanála [2026] IEHC 36 (Unreported, High Court, Farrell J., 3 February 2026)

§32

; and (iii) intensification can require permission and thus defeat any seven year defence: Patterson v. Murphy [1978] I.L.R.M. 85 (Costello J.); Butler v. Dublin Corporation [1999] IESC 19, [1999] 1 I.R. 565, [1999] 1 I.L.R.M. 481; Kildare County Council 23 v. Goode [1999] IESC 43, [1999] 2 I.R. 495, [2000] 1 I.L.R.M. 346; In Lanigan and Benghazi Ltd t/a Tullamaine Castle Stud v. Barry and Motor Speedway Ltd t/a Tipperary Raceway [2008] IEHC 29 (Unreported, High Court, Charleton J., 15 February 2008); Cork County Council & Ors v. Slattery Pre Cast Concrete Ltd & Ors [2008] IEHC 291 (Unreported, High Court, Clarke J., 19 September 2008); Lanigan v. Barry [2016] IESC 46, [2016] 1 I.R. 656 (

§5.5 per Clarke J.; Denham C.J.

and Dunne J. concurring).”

  1. It is clearly established that significant works commenced in mid-August
  2. These works resulted in significant new development, site clearance, excavation, tree felling, hard standing and the replacement of mobile home-type structures with block built modular homes. On any realitybased analysis, this is a new development. Hence even on the basis that there was a previous caravan/ mobile home park-type development for more than seven years, the various changes and intensifications since then mean that we are dealing now with a new development which cannot avail of the seven-year defence.
  3. More specifically, the removal of an unauthorised structure that would have benefitted from a defence does not give rise to an entitlement to reinstate such a structure without permission, because that would in itself be a new development.
  4. There was an ancillary, unstateable, argument by the respondents that there was an established “use” as a caravan/ mobile home park which precluded enforcement. The reason that is unstateable is twofold. Firstly it gets the respondents nowhere in terms of the legality of works. Secondly, even assuming in their favour that there was such an established use while the caravans/ mobile homes were in place, the lawful exercise of that use requires structures. The respondents themselves have in substance removed all of the previous structures (I deal below with the lastditch defence that there were fragments of foundations underneath new concrete), so there are no structures there by reference to which any such use could be carried out. Hence the removal of the last caravan/ mobile home with a view to being replaced by the present house-type structures terminated the lawful established use by caravans/ mobile homes. Any resumed use in the latter regard would be a new development. Estoppel and so on simply doesn’t arise once the use ceases. Issue 4 – whether tree-cutting is development
  5. Section 3 of the 2000 Act defines development: “Development. 3.—

(1)In this Act, except where the context otherwise requires, ‘development’ means— (
  1. a)the carrying out of any works in, on, over or under land, or the making of any material change in the use of any land or structures situated on land, or (
  2. b)development within the meaning of Part XXI (inserted by section 171 of the Maritime Area Planning Act 2021).
(2)For the purposes of subsection
(1)and without prejudice to the generality of that subsection— (
  1. a)where any structure or other land or any tree or other object on land becomes used for the exhibition of advertisements, or (
  2. b)where land becomes used for any of the following purposes— (
  3. i)the placing or keeping of any vans, tents or other objects, whether or not moveable and whether or not collapsible, for the purpose of caravanning or camping or habitation or the sale of goods, (
  4. ii)the storage of caravans or tents, or (iii) the deposit of vehicles whether or not usable for the purpose for which they were constructed or last used, old metal, mining or industrial waste, builders’ waste, rubbish or debris, the use of the land shall be taken as having materially changed.
(3)For the avoidance of doubt, it is hereby declared that, for the purposes of this section, the use as two or more dwellings of any house previously used as a single dwelling involves a material change in the use of the structure and of each part thereof which is so used.” 133. Section 3
(2)(
  1. a)draws an implicit distinction between a “structure” and a “tree or other object”. This is not an unquestionably natural distinction because the normal meaning of “object” does not suggest immoveable living natural beings. 134. Section 2 defines “structure”: “‘structure’ means any building, structure, excavation, or other thing constructed or made on, in or under any land, or any part of a structure so defined, and— (
  2. a)where the context so admits, includes the land on, in or under which the structure is situate, and (
  3. b)in relation to a protected structure or proposed protected structure, includes— (
  4. i)the interior of the structure, (
  5. ii)the land lying within the curtilage of the structure, 24 (iii) any other structures lying within that curtilage and their interiors, and (
  6. iv)all fixtures and features which form part of the interior or exterior of any structure or structures referred to in subparagraph (
  7. i)or (iii);” 135. Thus structures are either human made constructions or the land in, on or under which they are made. Given that “structure” includes the land on which it is situated, we will not be surprised

the somewhat circular definition of “land”: “‘land’ includes any structure and any land covered with water (whether inland or coastal);”

  1. The key point is that “land” includes the natural environment even though “structure” is directed to the built environment.
  2. Thus cutting a tree or a hedge is the carrying out of “works” on “land” and thus is “development”.
  3. Such a reading leads to a coherent interpretation of the 2000 Act. It therefore makes sense that the definition of “exempted development” in s. 4

(1)includes the following (which would not be necessary if works on trees were not development): “(i) development consisting of the thinning, felling or replanting of trees, forests or woodlands or works ancillary to that development, but not including the replacement of broadleaf high forest by conifer species;” 139. Section 34
(4)(
  1. e)allows tree planting to be conditioned by the imposition of: “(
  2. e)conditions for requiring the planting, maintenance and replacement of trees, shrubs or other plants or the landscaping of structures or other land;” 140. The fifth schedule includes this as a non-compensatable condition and extends it to flowers: “20. Any condition relating to the preservation and protection of trees, shrubs, plants and flowers.” 141. In summary therefore, tree felling/ thinning (or cutting of hedges, shrubs, flowers or other plants) is indeed development, subject to consideration of exemptions. For good measure this is consistent with Doorly v. Corrigan [2022] IECA 6 (Unreported, Court of Appeal, 21 January 2022). Issue 5 – whether the development is exempted development under s. 4
(1)(h) of the 2000 Act 142. The parties’ positions in the SDCC case as recorded in the statement of case are summarised as follows: “Main Issue Is the development exempted development under s.4
(1)(h) of the PDA? Respondent’s Position: 1. As appears from their Affidavit evidence before the Circuit Court, the only basis upon which the Appellants opposed the Council’s application for injunctive relief under s.160 of the PDA was on the basis that same comprised exempted development for the purposes of s.4
(1)(h) of the PDA. This position is [maintained] on appeal (as appears from the further Affidavits filed before the High Court – which, as outlined in Written Submissions, the Council is objecting to). 2. The Appellants’ arguments in this regard are entirely misconceived. The following points can be noted: This case concerns significant unauthorised development of multiple dwelling-type structures and extensive unauthorised site development works by the Appellants on lands located

Chianti Park, Mount Seskin Road, Raheen, Brittas, Co Dublin. As is clear from the Council’s photograph exhibits, the structures previously located on the lands comprised mobile homes (this is not disputed) while the structures now on the lands are dwelling houses. The exhibits illustrate the full extent of the unauthorised site clearance works and the construction, from the ground up, of these new dwelling structures. Section 4

(1)(h) is concerned with works which make insignificant differences (improvements/maintenance/alterations) to existing structures. It does not apply to works which comprise the total or substantial replacement of the original structure. It does not apply to development which involves the demolition of one structure and the construction of an entirely new structure. It does not apply to site clearance works. It is completely unsustainable to suggest, as the Appellants do, that these new unauthorised structures comprise the maintenance and improvement of the previous structures (mostly mobile homes) located on the Lands. The Appellants’ position is utterly un-stateable. The structures now on the Lands are completely different to the [structures] previously located on same. There is no pre-existing structure which is subject to some form of maintenance or improvement works (per s.4
(1)(h)), so that the same structure remains but has been improved or repaired for maintenance. The structures are not even similar – the previous structures comprise mostly mobile homes, while what has now been constructed on the Lands are new permanent dwellings. They are different in size, shape, 25 143. design, materials, etc. The Appellants’ reliance on s.4
(1)(h) of the PDA is entirely without substance. The onus of proof is on the Appellants to demonstrate that they fall within the exemption - which they have failed to discharge. In terms of discretion (noting that the Appellants did not address this in the Circuit Court), as detailed in the Council’s submissions, all of the relevant factors which the Court can consider (per Meath County Council v Murray [2018] 1 IR 189) weigh in favour of affirming the Circuit Court Order. Appellants’ Posiiton [sic]:
  1. The site is long established as a residential use and development. The documents on file state this use has been established pre October
  2. The SDCC Development Plan 2022-2028 land use Zoning Map shows the subject development as an existing established development within the context of the land use and heritage and other conservation objectives. The planning unit of the overall site of Hillsbrook Lawns and Chianti Park are included on the development plan zoning map and it is implicit that this forms the relevant planning unit.
  3. The works on site can be described in broad terms as; • the existing residential units were in poor condition and required improvement • that the works were limited to and incorporated the existing foundations to the existing structures which were generally retained, • the existing footprint of the structures and site layout was retained, and • and road and access and entrance arrangements were retained. • Existing site infrastructure and services were retained. • That the works were confined to the footprint of the existing structure and land under the structure.
  4. The works, subject matter of the complaint, are an exempted development because they fall within statutory exemption contained within Section 4
(1)(h) of the Planning and Development Act 2000, as amended. 4. The exemption clearly provides therefore that if a person is carrying out works, that is any construction, demolition, excavation, alteration, improvement, repair or renewal of anything or part of a thing made or constructed on land then this falls with a category of the exemption) specifically that category of exemption provided under Section 4
(1)(h) of the Planning and Development Act 2000, as amended. 5. There is no doubt that these works complained of fall into

least three categories of activity provided for in Section 4

(1)(h) namely works for the ‘maintenance’ and/or ‘improvement’ and/or ‘alteration’ of a structure. 6. These structures were the subject matter of a survey conducted by the Respondents architect (who’s [sic] qualifications and expertise are not disputed) and who confirms that the foundations of these structures were retained and improved and that the alteration/improvement works are carried out on or within the footprint of those foundations. This is the only evidence of actual survey which is averred to

paragraph 7 of the affidavit of Adrian Donoghue and therefore as a matter of evidence has not been put in dispute and must be accepted. 7. These works prima facie exempted development so long as they comply with the second element of the exemption contained in Section 4

(1)(h) of the Planning and Development Act 2000, as amended.
  1. The only limitation provided for in this statutory exemption is that where the works materially affect the external appearance of the structure they are exempted development so long as they do not render the appearance of that structure inconsistent with its own character or the character of neighbouring structures.
  2. The appearance of the said structures are consistent with the character of the original structures being of the same size height, and design constructed as it has been on the original footprint of the existing structure. It has similar lightweight materials, fenestration, design and has exhibited a drawing of the design of the original structure and a drawing of the design of the new structure to demonstrate the non-material nature of the alteration.
  3. The Appellant/Respondents submit that exempted development is specifically excluded from the definition of unauthorised development/ unauthorised works that the works being carried out by the Respondent constitute exempted development and accordingly they cannot amount to an unauthorised development for the purposes of Section 2 of the Planning and Development Act 2000, as amended.” In the O’Neill case the statement of case records as follows: “Applicants’ Position 26
  4. The Applicant’s position is that the Respondents have carried out, and continue to carry out, a substantial and ongoing programme of unauthorised development

Chianti Park, Mount Seskin, consisting of site clearance, demolition of existing structures, construction of new modular homes, and the laying of new foundations. The Applicant submits that there is no planning permission for these works, no valid basis for exempted development under the Planning and Development Act 2000, and that the works go well beyond maintenance or alteration of existing structures. The Applicant relies on extensive affidavit and photographic evidence showing continued development, including on land where there were no structures prior to the commencement of the unauthorised development. 43. The Applicant further contends that the Respondents’

tempt to rely on exemptions under section 4

(1)(h) of the Act is legally and factually unsustainable. It is argued that the exemption only applies to works affecting existing structures and cannot cover demolition and complete replacement of structures, nor the construction of entirely new dwellings. The Applicant relies on established case law, including authorities confirming that exemptions must be strictly construed and do not extend to substantial rebuilding or replacement. On that basis, the Applicant submits that the Respondents’ activities constitute ‘unauthorised development’ within the meaning of the Act and cannot be retrospectively justified.
  1. Finally, the Applicant argues that the Court should exercise its discretion under section 160 in favour of granting relief because there is a clear and continuing breach of the planning code, with works proceeding despite complaints, engagement with the planning authority, and the commencement of proceedings. The Applicant emphasises that the development has significant planning and environmental impacts, including drainage issues affecting nearby residents, and that allowing it to continue would undermine the integrity of the planning system. Accordingly, the Applicant seeks orders restraining further works and requiring restoration of the land to its prior condition, with no stay on any such orders. The Respondent’s Position
  2. The site is long established as a residential use and development. The documents on file state this use has been established pre October
  3. The SDCC Development Plan 2022-2028 land use Zoning Map shows the subject development as an existing established development within the context of the land use and heritage and other conservation objectives. The planning unit of the overall site of Hillsbrook Lawns and Chianti Park are included on the development plan zoning map and it is implicit that this forms the relevant planning unit.
  4. The works on site can be described in broad terms as; • the existing residential units were in poor condition and required improvement • that the works were limited to and incorporated the existing foundations to the existing structures which were generally retained, • the existing footprint of the structures and site layout was retained, and • and road and access and entrance arrangements were retained. • Existing site infrastructure and services were retained. • That the works were confined to the footprint of the existing structure and land under the structure.
  5. The works, subject matter of the complaint, are an exempted development because they fall within statutory exemption contained within Section 4
(1)(h) of the Planning and Development Act 2000, as amended. 48. The exemption clearly provides therefore that if a person is carrying out works, that is any construction, demolition, excavation, alteration, improvement, repair or renewal of anything or part of a thing made or constructed on land then this falls with a category of the exemption) specifically that category of exemption provided under Section 4
(1)(h) of the Planning and Development Act 2000, as amended. 49. There is no doubt that these works complained of fall into

least three categories of activity provided for in Section 4

(1)(h) namely works for the ‘maintenance’ and/or ‘improvement’ and/or ‘alteration’ of a structure. 50. These structures were the subject matter of a survey conducted by the Respondents architect (who’s qualifications and expertise are not disputed) and who confirms that the foundations of these structures were retained and improved and that the alteration/improvement works are carried out on or within the footprint of those foundations. This is the only evidence of actual survey which is averred to

paragraph 7 of the affidavit of Adrian Donoghue and therefore as a matter of evidence has not been put in dispute and must be accepted. 27 51. These works prima facie exempted development so long as they comply with the second element of the exemption contained in Section 4

(1)(h) of the Planning and Development Act 2000, as amended. 52. The only limitation provided for in this statutory

🔗 To official source

AI explanation based on the official legal text. Indicative, not a substitute for legal advice.