Article 23. Explanation and Changes of Tender Documents

Obsah (7)Article 23Article 12Article 32Article 33Article 1Article 26Article 29

Article 23

. Explanation and Changes

Tender Documents

ficial translation LAW ON THE AMENDMENT

THE LAW ON PUBLIC PROCUREMENT 13 August 1996, No. I-1491 (as amended by 3 June 1999 No. VIII- 1210, 21 March 2000 No. VIII-1577) Vilnius Article 1. New Version

the Law

the Republic

Lithuania on Public Procurement The Law

the Republic

Lithuania on Public Procurement shall be amended and set forth to read as follows: “LAW

THE R REPUBLIC

LITHUANIA ON PUBLIC PROCUREMENT CHAPTER ONE GENERAL PROVISIONS Article 1. The Objective

this Law 1. This Law shall regulate: 1) the procedure

procurement by state and local authorities, public undertakings (including those specified in subparagraph 3 hereof),

fices or organisations

goods or services the value whereof during the financial year is not less than LTL 75 000 or

public works the value whereof is not less than LTL 300 000, executed with the resources

the State Budget, municipal budgets, the budgets

the State Social Insurance Fund and the Compulsory Health Insurance Fund and other state money funds, also resources received in the name

the State as charity or any other financial support, when the charity donor does not specify the purpose for which it should be used, also with funds received as loans on behalf

the State or loans received with State guarantee, unless the loan use agreements provide for other terms and conditions for the use

the loans; 2) procurement by the Bank

Lithuania, with the funds

the Bank

Lithuania,

goods or services the value whereof during the financial year is not less than LTL 75 000 or

public works the value whereof is not less than LTL 300 000; 3) procurement

goods or services the value whereof during the financial year is not less than LTL 1.8m or public works the value whereof is not less than LTL 1m, when the contracting authorities are state or municipality controlled undertakings or branches

undertakings that are on the list approved by the Government, operating in the water, energy, transport and telecommunications sectors as well as undertakings which have had the special or exclusive right

operation in the sphere granted to them by the state or municipality, irrespective

the types

undertakings or forms

their ownership when such procurement is financed with the funds

the above undertakings. 2. The procurement

goods, services or works the value whereof is less than the amounts specified in paragraph 1 hereof shall be effected in accordance with the procedure laid down by the Government

the Republic

Lithuania. The Government may approve the list

goods, works, services in respect whereof public procurement shall apply in any case, regardless

their value. 3. Public procurement

goods, works or services, the value whereof is not less than that specified in paragraph 3

Article 12

this Law and an international notice whereof must be published in a publication with international circulation or specialised publication, may be engaged in only by contracting authorities included in the list approved by the Government

the Republic

Lithuania or by the competent authority. 4. The value

public procurement regulated under paragraph 1 hereof, paragraph 3

Article 32

and paragraph 1

Article 33

is given net

the VAT. The value shall be indexed in the manner laid down by the Government

the Republic

Lithuania or the competent authority taking into account the rate

inflation in the Republic

Lithuania. 5. The requirements

this Law shall not apply to: 1) procurement connected with state secret established by law. The procedure

procurement

the type shall be established by the Government

the Republic

Lithuania; 2) procurement carried out following the special procurement procedures

international organisations; 3) procurement or lease

land or other immovable property effected by undertakings specified in subparagraph 3

paragraph 1 hereof with the funds

the said undertakings, provided the procurement or lease in a specific location is necessitated by the intended purpose

the undertaking; 4) financial services connected with the issuing, purchase, sale and transfer

securities and other instruments

debt; 5) services provided by the Bank

Lithuania; 6) contracts for the acquisition

time for radio and television programme development, preparation for broadcasting, broadcasting

already developed radio and television broadcasts, except when the procurement is engaged in by state or local authorities; 7) research and development services

national significance according to the programmes approved by the Government, except for those research and development services the benefit from which is used solely for business needs

the contracting authority and which are fully paid for by the contracting authority. 6. The Government

the Republic

Lithuania may, for economic and social reasons which are

state significance, take a decision regarding the application

preferences during the procurement

goods, works or services. The provision shall apply until the expiry

the transitional period specified in the Europe Agreement establishing an Association between the European Communities and their Member States,

the one part, and the Republic

Lithuania,

the other part (31 December 1999). Article

  1. Definitions As used in this Law:
  2. “Public procurement” (hereinafter referred to as procurement ) means the acquisition

goods, works or services (including lease

property) carried out in the manner prescribed by this Law by contracting authorities specified in paragraph 1

Article 1and paid for on demand or by instalments.

  1. “Open procedure” means procurement procedure under which all interested suppliers/contractors may submit their tenders.
  2. “Works” means any works associated with the construction (assemblage, building), reconstruction, removal, demolition, repairs or renovation

structures as well as research, design or other services incidental to the works which are the object

procurement. 4. “Discount price” means a price recalculated taking into account the time limits

payments, supply

goods, provision

services and performance

works.

  1. “Financial year” means a 12-month period beginning 1 January and ending 31 December.
  2. “Final tender” means the supplier’s/contractor’s written document whereby an

fer is made to supply goods, provide services or perform works in accordance with the terms agreed upon in the course

negotiated procedure. 7. “Undertaking possessing the special or exclusive right granted by the state or municipality to operate in the water, energy, transport and telecommunications sectors” means an undertaking to which the state or municipality has granted a special or exclusive right to engage in any type

activities specified in paragraph 27 hereof. 8. “Request for quotations” means procurement procedure where the procuring entity requests from the suppliers/contractors a statement

the price

goods or services. 9. “Negotiated procedure” means procurement procedure where the procuring entity negotiates with the suppliers/contractors the contents

tenders and the terms

the contract. 10. “Invitation” means a procurement-related document announced or delivered to the supplier (contractor),

fering an invitation to participate in prequalification proceedings, tendering, negotiated procedure or to respond to the request for quotations.

  1. “Legalised documents” means documents recognised as lawful according to the procedure prescribed by law.
  2. “Declaration

impartiality” means a written statement given by the Public Procurement Commission member or expert declaring his impartiality with respect to the suppliers/contractors.

  1. “Application” means a document whereby the supplier (contract) expresses his willingness to take part in the procurement procedures.
  2. ”Tender” means a written document submitted by the supplier/contractor

fering to supply goods, perform works or provide services under the terms set by the contracting authority. 15. “Tender security/(security for the performance

the contract)” means the method

ensuring the fulfilment

an obligation provided for by the Civil Code

the Republic

Lithuania, perfected by the contract between the contracting authority and the supplier/contractor. 16. “

fered price” means the sum total

the price

goods, services or works indicated in the tender and other prices

additional services specified in the procurement documents. 17. “Discounting

the

fered price” means recalculation

the

fered price (carried out for the purpose

tender evaluation) by applying the rate fixed in advance (the rate

discount), taking into account the time limit for payment and supply

goods, provision

services, and performance

works. 18. “Services” means any object

procurement, except for goods and works, as well as services related to goods, where the value

the services exceeds the value

goods. 19. Contracting authority means the state or local authority, public undertaking,

fice or organisation specified in paragraph 1

Article 1

as well as the Bank

Lithuania. 20. “Procurement from single source

supply” means procurement procedure where the contracting authority negotiates with a single supplier/contractor the subject and price

the

fers and the terms

the contract. 21. “Contract documents” means documents presented by the contracting authority to the suppliers/contractors characterising the subject

the procurement contract and the conditions

procurement: the invitation, tender solicitation documents and documents

other procurement procedures and conditions, explications/revisions

and supplements to the above documents. 22. “Contract

procurement- sale” (hereinafter - “procurement contract”) means the contract

procurement-sale, contract agreement, work or service contract, contract

lease or other written contract which the contracting authority concludes with the supplier/contractor when procuring goods, services or works in the manner prescribed by this Law. 23. “Preference” means priority, privilege. 24. “Goods” means raw materials, goods, equipment and other objects

every kind and description, as well as services incidental to the supply

the goods if the value

those services does not exceed that

the goods themselves.

  1. “Restricted procedure” means the procurement procedures whereby only those suppliers/contractors who satisfy the qualification requirements announced in advance by the contracting authority may submit tenders.
  2. “Supplier/contractor” means a potential or actual party to the procurement contract concluded with the contracting authority.
  3. “Public undertaking operating in the water, energy, transport and telecommunications sectors” means a state or municipality-owned undertaking, also the undertaking in which public authorities control over 50%

votes attaching to shares and which exercises one

the following activities: 1) the operation

fixed networks intended to provide a service to the public in connection with the production, transport or distribution

drinking water, or electricity, or gas or heat; 2) the exploitation

a geographical area for the purpose

exploring for or extracting oil, gas, coal or other fossil fuels; 3) the provision

airport, maritime or inland port or other terminal facilities to carriers by air, sea or inland waterway; 4) the operation

networks providing a service to the public in the field

transport by trolley bus, bus, cable or railway; 5) the operation

public telecommunications networks and provision

public telecommunications services. Article 3. International Obligations

the State, Relating to Procurement If international agreements

the Republic

Lithuania provide otherwise than this Law, the provisions

international agreements shall apply. Article 4. Regulation

Public Procurement and Examination

Complaints 1. Public procurement in the Republic

Lithuania shall be regulated by the Government and the Public Procurement

fice, who shall be governed by this Law, whereas complaints relating to public procurement shall be examined by the Independent Commission for the Examination

Complaints Relating to Public Procurement. Article 5. Public Procurement

fice 1. Public Procurement

fice is an institution operating under the Government

the Republic

Lithuania, which co-ordinates the activities

procurement, supervises compliance

procurement activities with this Law and subordinate legislation, is governed by this and other laws, legal acts and international obligations

the Republic

Lithuania and its own regulations and is financed from the State Budget. 2. Public Procurement

fice is a legal person, having its seal with the State emblem. 3. Public Procurement

fice shall fulfil the following functions: 1) draft and submit to the Government for approval legislation regulating public procurement; 2) draft and adopt, within the scope

its competence, legal acts regulating public procurement; 3) supervise compliance during public procurement proceedings with the Law on Public Procurement and the requirements

related secondary legislation; 4) approve the methodology

drawing up technical requirements

contract documents; 5) store, in the manner prescribed by the Government, information concerning the intended procurement or that being engaged in, the concluded procurement contracts and the contract performance results, and communicate it to state (local government) institutions and the public; 6) analyse and assess the procurement system and draw up proposals for its improvement; 7) organise the training

the contracting authorities’ personnel responsible for procurement and train the personnel 8)

fer consultations to contracting authorities and suppliers/contractors or organise their consulting on issues

procurement; 9) when deciding the issues

procurement, maintain contacts with the relevant foreign state institutions and international organisations; 10) specify the mandatory requirements

communications (prior indicative notices, invitations, and contract award notices and contract performance results); 11) approve the methodology

calculating the estimated contract value, specify the procedure for discounting the price

fered by the suppliers/contractors and fixing the rate

discount; 12) approve standard forms

procurement reports; 13) lay down the requirements for the members

the Independent Commission for the Examination

Complaints Relating to Public Procurement; 14) prepare and furnish information to the Independent Commission for the Examination

Complaints Relating to Public Procurement which examines the complaints; 15) engage in other activities prescribed by legal acts. 4. Rights

the Public Procurement

fice: 1) to be provided by the contracting authority with information relating to procurement; 2) to be provided by the contracting authority, Public Procurement Commission or its members as well as experts taking part in procurement procedures explications

procurement-related actions or decisions; 3) to present contract documents and tenders submitted by suppliers/contractors for additional expert examination; 4) upon ascertaining violations

law, to obligate the contracting authority to revoke or to change the decisions or actions which are not in conformity with the requirements

the Law on Public Procurement; 5) to take administrative proceedings in the manner prescribed by law against the persons who violate this Law. Article

  1. Public Procurement Commission
  2. For arranging and executing procurement, the contracting authority must appoint the Public Procurement Commission (hereinafter - Commission), set its tasks and grant it the powers required for the fulfilment

said tasks. The Commission shall be accountable to the contracting authority and fulfil only its tasks and obligations given in writing. The responsibility for awarding and fulfilling procurement contracts shall rest with the contracting authority. The contracting authority shall be responsible for the actions

the Commission. The contracting authority shall approve the Commission’s rules

procedure. 2. The Commission shall be appointed by the decision

the contracting authority

at least 3 natural persons, who may also be employed on a contract basis, and shall function on behalf

the contracting authority within the scope

the powers granted to it. The Commission shall function from the day

adoption

the decision concerning its appointment until the submission

the draft

the procurement contract to the contracting authority for signing or until the adoption

the decision to terminate the procurement. The Commission shall adopt decisions at the meetings by a simple majority vote, voting by open ballot. In the event

a tie, the Chairman

the Commission shall have a casting vote. The Commission’s decisions shall be recorded in the minutes signed by all the members present at the meeting. The head

the contracting authority or the person authorised by him shall be appointed Chairman

the Commission. When appointing Commission members, regard must be had to their knowledge in the area

economics, technology, and legislation as well as their cognisance

this Law and other legal acts regulating public procurement. The contracting authority shall have the right to invite experts for examining the submitted proposals. 3. Except in cases prescribed by the legal acts

the Republic

Lithuania, the Commission members and the experts invited by the contracting authority shall be prohibited from providing third persons with any information concerning the contents

the tenders submitted by suppliers/contractors. 4. Every Commission member and expert may take part in the work

the Commission only upon signing the declaration

impartiality. 5. Commission members and experts shall be held liable for their work under the laws

the Republic

Lithuania. Article 7. Qualification

Suppliers/Contractors 1. The contracting authority must ascertain whether the supplier/contractor is competent, reliable and capable to fulfil procurement conditions. For this purpose, at certain stages

the procurement process it shall have the right to demand that the supplier/contractor submit the documents and information specified in paragraph 2 hereof. 2. The contracting authority shall specify in the contract documents the information relating to the legal status, financial standing, also economic and technical information that the suppliers/contractors must provide so as to enable the contracting authority to determine whether the suppliers/contractors satisfy the minimum financial, economic and technical requirements laid down in its contract documents. The contracting authority may request that the suppliers/contractors submit: 1) documents confirming the suppliers’/contractors’ legal status; 2) extracts from reports or other documents confirming the activities

the suppliers/contractors (unless under the laws

the country where the supplier/contractor is domiciled the reports or documents are not subject to publication); 3) extracts from reports or other documents concerning the supplier’s/contractor’s total turnover and the turnover relating to the object

procurement within the last 3-year period or within the time period from the date

the supplier’s/contractor’s registration (in case the supplier/contractor engaged in the activities for less than a 3-year period); 4) where the supplier/contractor is not in the position to submit documents specified in subparagraph 2 hereof, the contracting authority may accept other information which it deems to be appropriate; 5) information concerning the principal supplies

goods made, works performed or services provided, specifying the procuring entities and contracts executed earlier within the last 3 years or within the period from the supplier’s/contractor’s registration date (where the supplier/contractor engaged in the activities for less than 3 years); 6) information concerning the supplier’s/contractor’s technical possibilities and other measures ensuring good quality

the goods supplied, works performed or services provided by him; 7) information about the specialists or organisations responsible for quality control, irrespective

their subordination; 8) certificates drawn up by

ficial quality control institutes or agencies attesting conforming

the goods, works or services to the binding technical specifications; 9) description, samples or photographs

the goods to be supplied, works to be performed or services to be provided by the supplier/contractor. Where the goods to be supplied are complex or are required for a special purpose, the contracting authority may request the supplier’s/contractor’s permission to carry out on-the-spot inspection

the good to be supplied or demand that the information furnished by the supplier/contractor be evaluated by independent experts; 10) evidence

the educational and professional qualifications

the supplier’s/contractor’s managerial staff,

the persons responsible (in particular those responsible for the execution

works); 11) a statement evidencing the supplier’s/contractor’s financial standing; 12) other financial, economic and technical information specified by the Public Procurement

fice. 3. Qualification requirements set by the contracting authority, the criteria for their evaluation and the evaluation procedures shall be laid down in the contract documents. The documents must be furnished to the suppliers/contractors only after the publishing

the notice in the publications specified in Article 12

this Law.

  1. The same qualification requirements must be applied with respect to all suppliers/contractors, the requirements may not violate the supplier’s/contractor’s rights to protect intellectual property, a trade or commercial secret.
  2. The contracting authority may not impose on the suppliers/contractors requirements which would prejudice fair competition.
  3. The contracting authority shall have no right to reject the suppliers’/contractors’ tenders on the grounds

the tenders having been submitted by natural persons or a group

suppliers/contractors who have formed a joint venture. The joint venture agreement must be notarised. The contracting authority shall award a contract only after the group

suppliers/contractors have registered, according to the procedure laid down by law, the undertaking on the basis

the joint venture agreement.

  1. The contracting authority must reject the supplier’s/contractor’s application or tender if the Commission establishes that the supplier/contractor submitted inaccurate or incomplete information concerning the qualifications and if the supplier/contractor fails to remedy the deficiencies within 3 working days upon request by the contracting party. The contracting authority shall within 3 working days notify the supplier/contractor thereof in writing.
  2. The qualifications

the suppliers/contractors shall be evaluated in accordance with the criteria and procedures set forth in contract documents presented to them. The Commission shall make a decision regarding the qualifications

each supplier/contractor who submitted an application and shall notify each one

them

the verification results. Only the suppliers/contractors whose qualifications meet the requirements

the contracting authority shall be entitled to participate in the subsequent procurement procedures. Article 8. Method

Notification 1. While carrying out the procedures regulated by this Law, the notices

the contracting authority and suppliers/contractors to each other must be transmitted in writing.

  1. The contracting authority must ensure that the contract documents, decisions or other notices be transmitted to all suppliers/contractors under equal conditions. Article
  2. Legalisation

the Documents Submitted by Foreign Suppliers/Contractors The contracting authority shall have the right to demand that foreign suppliers/contractors submit documents confirming their qualifications legalised in the established manner. Article 10. Description

Goods, Works or Services 1. Technical specifications

goods, works or services indicated in the procurement documents (requirements concerning their quality, packaging, marking, safety, certification, testing) as well as the terminology must not create obstacles for participation by any suppliers/contractors in the procurement procedures, except where such specifications are necessary by reason

the specific character

the object

procurement or its application. The description

goods, works or services shall not contain any indication

a particular trade mark, patent, type or specific origin or producer

the good, the trademarks, patents, models or origin

goods, performers

works or providers

services. However, where such indication is accompanied by the words “or equivalent”, it shall be authorised in cases where the contracting authorities are unable to give a description

the subject

the contract using specifications which are sufficiently precise and intelligible to all parties concerned. 2. In the descriptions

goods, works or services, including contract documents, submitted technical specifications, plans, drawings and designs international standards, marking and terminology must be used. Where such international standards are not available, the terminology and marking requirements accepted in the Republic

Lithuania shall be used. 3. The methodology for developing technical requirements to be presented in contract documents shall be approved by the Public Procurement

fice. Article 11. The Language

Documents The contracting authority shall draw up contract documents in the state language. When, according to the requirements set forth in Article 12

(3)

this Law, notices

procurement are published in a publication with international circulation or special publication, foreign suppliers/contractors shall be provided contract documents in the English language or, if they so desire, also either in German, or French, or Russian. Article 12. Notices 1. The requirements for notices (prior notices, invitations, contract award notices and contract performance results) shall be laid down by the Public Procurement

fice. 2. The contracting authority shall: 1) make known, in accordance with the procedure prescribed by the Government, by means

the indicative notice the total procurement envisaged to be awarded during the current financial year, published in the supplement to the publication “Valstybës þinios” - “Informaciniai praneðimai” and, in the cases specified in paragraph 3 hereof, also in the publication with international circulation or specialised publication; 2) every time wishing to award a contract by open, restricted or negotiated procedure or by request for quotations, besides the indicative notice specified in subparagraph 1 hereof, also publish invitations to participate in the procurement procedure in the supplement to the publication “Valstybës þinios” - “Infromaciniai praneðimai” and, in the cases specified in paragraph 3 hereof, also in the publication with international circulation or specialised publication; 3) publish notices

the awarded contracts in the supplement to the publication “Valstybës þinios” - “”Informaciûniai praneðimai”. The notices shall be dispatched to the publication “Valstybës þinios” within 5 days after the award

the contract. The notice shall indicate the entity to whom the contract is awarded, the subject

the procurement contract, the price indicated in the contract and the discounted price; 4) Within 15 days after the performance

the procurement contract publish a notice in the special supplement to the publication “Valstybës þinios”- “Informaciniai praneðimai” announcing the contract performance results, the price

procurement and the discount price. 3. The contracting authority must publish notices

public procurement in the publication with international circulation or specialised publication if: 1) the estimated value

goods to be procured is not less than LTL 700,000, and not less than LTL 1.8 m in case

procurement in

water, energy, transport sectors, and not less than LTL 2.7 m in the telecommunications sector; 2) the estimated value

services to be procured is not less than LTL 700,000, and in the field

water, energy, transport and telecommunications sectors - not less than LTL 1.8 m; 3) the estimated value

works to be procured is not less than LTL 22 m. 4. The estimated value

procurement contracts is indicated in paragraph 3 hereof net

VAT. The figures shall be revised every 2 years with due regard being had

the revised value as indicated in the EU directives. CHAPTER II PROCUREMENT PROCEDURES SECTION I PROCUREMENT PROCEDURES, THEIR CHOICE AND INDIVISIBILITY

PROCUREMENT CONTRACTS Article 13. Public Procurement Procedures Public procurement shall be engaged in according to the following procedures: 1) open procedure; 2) restricted procedure; 3) negotiated procedure; 4) procurement from single source

supply; 5) request for quotations. Article 14. Manner for Choosing Procurement Procedure The contracting authority may choose procurement procedure - either negotiated procedure or procurement from single source

supply, or request for quotations - only under the conditions provided for in Chapter Two, Sections IV, V and VI,

this Law. In addition, in the case specified in paragraph 2

(7)

Article 32

this Law, the Government may establish that the consent to execute procurement from single source

supply or according to any other procedure, as established in the procurement regulations approved by the contracting authority, shall be effective not for a specific case

procurement, but for the entire period

the investment or commercial project (including projects financed with borrowed funds) implemented by the contracting authority; the above period shall be approved by the Government

the Republic

Lithuania. In other cases procurement shall be effected by means

tendering procedure. Article 15. Indivisibility

Procurement Contracts 1. The contracting authority shall have no right to split up the value

procurement contract if this would enable to avoid the procurement procedure established by this Law. The contracting authority shall have the right to split up the value

a procurement contract only provided that procurement procedure chosen under this Law for the total value

procurement contract is applied with respect to all parts

the split up value

procurement . 2. The contracting authority shall award procurement contract under this Law on the basis

the total value

the contract (as regards the value

goods and services - the total value during the financial year, as regards the value

works - the value

the entire object). 3. The value

procurement contract shall be calculated and the goods, services and works shall be identified (distinguished from those identical) in accordance with the methodology approved by the Public Procurement

fice. SECTION II OPEN PROCEDURE Article 16. Open Procedure When making arrangements for an open procedure, the contracting authority shall invite, in the manner laid down in Article 12

this Law, all suppliers/contractors to take part in the procedure and submit their tenders. Article 17. Contents

the Invitation to Tender An invitation to tender must contain the following information: 1) the name, code, address, phone and fax numbers

the contracting authority; 2) the name and quantity

goods to be supplied, the address

their delivery, character and place

services to be provided or works to be performed; 3) desired or required final date for the supply

goods, provision

services or completion

works; 4) the procedure and place for acquiring solicitation documents; 5) language (languages) in which solicitation documents must be drawn up; 6) if the contracting authority has fixed a charge for solicitation documents - the amount

the charge and payment procedure. The charge shall cover the actual costs

the drawing up and copying

documents and their delivery to the suppliers/contractors. Additional amount may be charged to cover the expenses relating to translation

documents into foreign languages; 7) the addressee

tenders and the date

tender submission; 8) other information prescribed by the Public Procurement

fice to the supplier (contractor). Article 18. Presentation

Solicitation Documents 1. The contracting authority shall present solicitation documents to the suppliers/contractors desiring to take part in the tendering procedure in the manner specified in the invitation to tender. A charge

an equal amount may be payable by all suppliers/contractors for covering actual expenses relating to the drawing up and copying

documents and their delivery to the suppliers/contractors. An extra charge may be payable for the translation

solicitation documents into a foreign language which will cover expenses relating to translation into a foreign language. 2. The contracting authority must deliver solicitation documents to the suppliers/contractors within 6 days from the receipt

their applications. Article 19. Contents

Solicitation Documents The following information shall be submitted in the solicitation documents: 1) instructions for preparing tenders; 2) information concerning the criteria and procedures relative to the evaluation

the qualifications

suppliers/contractors; 3) documentary evidence demonstrating the qualifications

suppliers/contractors; 4) names

goods, works or services to be procured and their required technical, aesthetic, functional and quality characteristics, plans, drawings and designs, the quantity

the goods, any incidental services to be performed, the required time when the goods are to be delivered, the services are to be provided and the works are to be performed, the running costs and other terms and conditions; 5) criteria and terms and conditions

tender valuation, procedure for discounting the

fered price and the rate

discount; 6) procedure and terms and conditions

price indexing owing to inflation; 7) terms and conditions

the contract

fered to the parties for signing by the contracting authority and the contract form, if any, to be signed by the parties; 8) if alternatives to the characteristics

the goods, services and works, contractual terms and conditions set forth in solicitation documents are permitted, a statement to the effect; 9) if, without infringing Article 15

this Law, the suppliers/contractors are authorised to submit tenders for only a portion

the goods, works or services concerned - a description

the portion or portions for which tenders may be submitted; 10) the manner in which tender price is to be formulated and expressed. The price shall be given with all the taxes due included. The price

goods, services and works and the prices

additional services specified in the solicitation documents (transportation, insurance, loading charges, etc.) must be calculated and presented separately; 11) requirements for tender security and security for the performance

the procurement contract; 12) final date, place and method

submission

tenders; 13) the means by which suppliers/contractors may seek clarification

the solicitation documents and a statement as to whether the contracting authority intends, at this stage, to convene, a meeting

suppliers/contractors; 14) the period

time during which tenders shall be in effect; 15) the place, date and time for the opening

envelopes with tenders; 16) the procedure to be followed for opening and examining tenders; 17) indication that the value

the object

procurement named in the tender will be calculated in litas. Where the prices are indicated in the tenders in foreign currency, the prices will be recalculated in litas according to litas and the foreign currency exchange rate determined and announced by the Bank

Lithuania on the day

tender evaluation; 18) full names, addresses, telephone and fax numbers

the

ficers and employees

the contracting authority, or the Commission members (one or several) who are authorised to communicate directly with and to receive communications directly from suppliers/contractors in connection with the procurement procedure, without the intervention

an intermediary; 19) other requirements laid down by the Public Procurement

fice in compliance with this Law and other legal acts regulating procurement; 20) reference to the prior publication

a tender notice in the information supplement to the publication “Valstybës þinios” - “Informaciniai praneðimai” and/or in the publication with international circulation or specialised publication. Article 20. Clarification

Solicitation Documents 1. Suppliers/contractors may request a clarification

the solicitation documents from the contracting authority. The contracting authority shall respond to any written request by a supplier/contractor for clarification/revision

the solicitation documents provided it is received not later than 15 days before the final date fixed for the submission

tenders. The contracting authority must respond to the request not later than within 6 days from the date

receipt

the request. When responding to a supplier/contractor the contracting authority shall simultaneously send explanations to all suppliers/contractors to whom it has presented contract documents, without identifying the source

the request. 2. At any time prior to the deadline for submission

tenders, the contracting authority may explain/revise the solicitation documents on its own initiative. The clarification/revision must be communicated to all suppliers/contractors to which the contracting authority has provided the solicitation documents not later than 9 days before the final date fixed for the submission

tenders. 3. If the contracting authority convenes a meeting

suppliers/contractors, it must prepare minutes

the meeting containing the requests submitted at the meeting for clarification

the solicitation documents, and its responses to those requests. Minutes must be dispatched to all suppliers/contractors taking -part in the procurement procedures not later than 9 days before the final date fixed for the submission

tenders. 4. If the contracting authority provides clarification/revision

the solicitation documents or convenes a meeting with the suppliers/contractors less than 9 days before the final date fixed for the submission

tenders, it must postpone the time limit fixed for the submission

tenders for a period enabling the suppliers/contractors to take the clarification/revision or minutes

the meetings into account in preparing their tenders. 5. Notices

the postponement

the final date fixed for the submission

tenders must be dispatched, not later than on the next working day following the adoption

the decision, to all suppliers/contractors to whom the solicitation documents have been presented. Article 21. Submission

Tenders 1. The contracting authority shall fix the date and the hour which shall be considered the deadline for the submission

tenders. The time period for the submission

tenders may not be less than 30 days from the publication

the invitation to tender in the information supplement to the publication “Valstybës þinios” - “Informaciniai praneðimai” and, in cases where the notice is published in a publication with international circulation or specialised publication, less than 52 days from the day

publishing

the invitation in the publication, except where a prior notice has been published in accordance with the procedure and within the time limit laid down in Article 12

this Law. In such cases the time period for the submission

tenders may be reduced accordingly to 20 and 36 days. 2. A written tender signed by the supplier/contractor or the person authorised by him shall be submitted in a sealed and stamped envelope. The tenders (with supplements) must be numbered, bound and endorsed by the supplier’s/contractor’s signature and stamp put on the back

the last sheet. 3. The contracting authority must present to each supplier/contractor a written confirmation

the receipt

the tender, indicating the date and hour

receipt. 4. If a tender is received after the expiry

the time limit set for the submission

tenders, the unopened envelope with the tender shall be returned to the supplier/contractor that submitted it. Article 22. Period

Effectiveness

Tenders; Modification and Withdrawal

Tenders 1. Tenders shall be in effect during the period

time specified in the solicitation documents which may not be longer than 90 days after the final date fixed for the submission

tenders. 2. Prior to the expiry

the period

effectiveness

tenders, the contracting authority may request suppliers/contractors to extend the period

tender effectiveness until the fixed deadline, without exceeding the time limit specified in paragraph 1 hereof. 3. Suppliers/contractors that agree to an extension

the period

effectiveness

their tenders and notify the contracting authority thereof in writing, shall extend the period

effectiveness

tender securities or provide new tender securities. A supplier/contractor that fails, within a 6-day period, to respond to the request

the contracting authority to extend the period

effectiveness

tenders or fails to extend the period

tender securities or to provide new tender securities, shall be considered to have refused the request to extend the period

effectiveness

its tender and to have withdrawn its tender. 4. Unless otherwise stipulated in the solicitation documents, the supplier/contractor may modify or withdraw its tender without forfeiting its tender security prior to the expiry

the time limit for the submission

tenders. The modification or notice

withdrawal shall be recognised as effective if it is received by the contracting authority prior to the expiry

the time limit for the submission

tenders. Article 23. Tender Security and Security for the Performance

the Contract 1.The contracting authority must request that the effectiveness

tenders and the performance

the contract be guaranteed in the manner established by the Code

Civil Procedure

the Republic

Lithuania. 2. The Commission may not reject the tender security or the security for the performance

the contract on the grounds that the security was not issued by the economic entity

the Republic

Lithuania provided that the tender security and the security for the performance

the contract and the economic entity who is the issuer

the security conform to the requirements set forth in the contract documents. 3. Prior to submitting a tender, a supplier/contractor may request the contracting authority to confirm the acceptability

the proposed issuer

a security. In this case the contracting authority shall respond to the supplier’s/contractor’s request within 3 working days. Confirmation

the acceptability

a proposed issuer shall not preclude the contracting authority from rejecting the tender security upon receipt

information that the issuer has become insolvent or defaulted on its obligations to the contracting authority or other economic entities, or otherwise lacks creditworthiness. 4. The Government

the Republic

Lithuania or the competent authority shall have the right to prescribe additional mandatory requirements for tender securities and securities for the performance

the contract. Article 24. Opening

Envelopes with Tenders 1. Envelopes with tenders shall be opened at the Commission meeting held at the place, at the date and hour specified in the solicitation documents. The date must coincide with the deadline for the submission

tenders. Upon changing the deadline, the date

opening

the envelopes with tenders must be changed accordingly. All envelopes with tenders received prior to the expiry

the time limit for their submission must be opened at the fixed time. All suppliers/contractors who submitted their tenders or their representatives shall have the right to participate in the envelope opening procedure. 2. The envelopes shall be opened by one

the Commission members in the presence

the suppliers/contractors attending the meeting, who submitted their tenders. 3. In conformity with the requirements prescribed by Article 21

this Law, the members present at the Commission meeting shall put their signatures at the back

the last sheet

the tenders. 4. The Commission shall record the results

the opening

envelopes in the record, mandatory requisites whereof shall be laid down by the Public Procurement

fice. 5. The name

the supplier who submitted the tender, his address and the price indicated in the tender, the time limits

payment, supply

goods, provision

services and performance

works shall be announced to the suppliers/contractors or their representatives, who are present at the opening envelopes with tenders. The information shall also be communicated to those suppliers/contractors who have submitted their tenders but are not present at the envelope opening procedure, if they so desire. Every supplier/contractor who is present or represented at the envelope opening procedure shall have the right

access in person to the information which is publicly read out. 6. The Commission shall engage in further tender examination, evaluation and comparison procedures without the participation

the suppliers/contractors who submitted the tender tenders. Article 25. Prohibition

Negotiations with Suppliers/contractors No negotiations shall take place between the contracting authority and a supplier/contractor with respect to the subject

the tender submitted by the supplier/contractor. Having proved the fact

illegal negotiations in the manner prescribed by law, the contracting authority shall declare the tendering procedure invalid in the information supplement to the publication “Valstybës þinios” - “Informaciniai praneðimai”, and legal proceedings shall be instituted against the guilty persons according to the procedure established by law. Article 26. Examination, Evaluation and Comparison

Tenders 1. The contracting authority may ask the suppliers/contractors for clarifications

their tenders. However, the contracting authority may not seek,

fer or permit any changes in a matter

substance in a tender, including changes in price and changes aimed at making an unresponsive tender responsive. 2. The contracting authority shall not accept a tender submitted by a supplier/contractor: 1) if the supplier/contractor that submitted the tender does not meet the qualification requirement set forth in Article 7

this Law and the solicitation documents; 2) if the tender is not responsive; 3) if the supplier (contractor) that submitted the tender has infringed the Law

the Republic

Lithuania on Competition; 4) if all suppliers/contractors have

fered disproportionately high prices unacceptable to the contracting authority; 5) if tenders appear to be abnormally low and the supplier (contractor) failed to substantiate the low prices as specified in paragraph 5 hereof. 3. If, for reasons indicated in paragraph 2 hereof, the Commission must reject all tenders, it must be given the authorisation

the Public Procurement

fice. 4. In the process

evaluation

the tenders the criterion for the award

contract shall be the lowest tender price, discounted taking into account the terms

payment and supply

goods, provision

services and performance

works, or the most economically advantageous tender. The procedure for discounting the tender price and the rate

discount shall be established by the Public Procurement

fice, whereas the methodology for establishing the criteria for evaluating the most economically advantageous tenders shall be approved by the Government

the Republic

Lithuania. 5. If, for a given contract, the tender appears to be abnormally low, the contracting authority must request in writing from the supplier/contractor substantiation

the constituent elements

the tender price. If the supplier/contractor fails to substantiate the tender price, its tender shall be rejected. The contracting authority shall notify the Public Procurement

fice

the reasons

the rejection

the tender and shall make a record thereof in the report on procurement procedures. 6. The Commission appointed by the contracting authority shall evaluate and compare only the responsive tenders submitted by the suppliers/contractors. In order to ascertain the successful tender, the Commission must: 1) evaluate, in accordance with the evaluation criteria and terms set forth in the solicitation documents, the tenders submitted by the suppliers/contractors and draw up a preliminary order

tenders (except for the cases

single-source procurement). The preliminary order

tenders shall be drawn up based on the increasing discounted tender prices. First in the order shall be the tender with the lowest discounted price; 2) notify the suppliers/contractors who submitted the tenders

the preliminary order

tenders and

the reasons for the rejection

tenders no later than on the next working day after the drawing up

the preliminary order

tenders; 3) approve the order

tenders and adopt a decision with respect to the successful tender only after the examination, according to the procedure established in Chapter Three

this Law,

the claims and complaints (if such were received)

the suppliers/contractors who submitted tenders, but no earlier than after 15 days from the day

dispatch to the suppliers/contractors

the notice

the preliminary order

tenders. 7. The notice

the successful tender shall be dispatched to all suppliers/contractors who submitted tenders not later than within 3 working days after the adoption

the Commission decision. 8. Access to the information relating to the examination, explication, evaluation and comparison

tenders, except for the information specified in Article 35

this Law, shall be granted only to the Commission members and experts invited by the Commission, representatives

the Public Procurement

fice and the Independent Commission for the Examination

Complaints Relating to Public Procurement, the head

the contracting authority and other persons and institutions entitled under the laws

the Republic

Lithuania to have access to the above information. 9. If, by the expiry

the time limit set by the contracting authority for the submission

tenders, less than 3 tenders are received or, upon rejection

tenders in conformity with the requirements

this Article, less than 3 tenders are left, tendering shall be considered not to have taken place and a notice to the effect shall be within 3 working days dispatched to all suppliers/contractors who submitted tenders. SECTION III RESTRICTED PROCEDURE Article 27. Restricted Procedure 1. Restricted procedures shall be engaged in where a large number

suppliers/contractors is expected and the cost

examination

tenders would be very high. 2. The contracting authority shall use restricted procedures by two rounds: 1) during the first round the contracting authority shall invite, in the manner set forth in Article 12

this Law, suppliers/contractors to participate in pre-qualification procedure and shall select according to the requirements set forth in the pre-qualification documents at least 10 qualifying suppliers/contractors from the suppliers/contractors who submitted applications to pre-qualify. Where during the first round applications to pre-qualify

less than 10 suppliers/contractors are received, the contracting authority shall invite to the second round all the suppliers/contractors who submitted applications and meet the qualification requirements set forth by the contracting authority; 2) during the second round every supplier (contractor) who has been pre-qualified in the first round shall be sent invitations to tender, and all suppliers/contractors who participated in the pre-qualification proceedings but were not selected to the second round shall be dispatched notices

the pre-qualification results. Invitations must be sent at the same time to all suppliers/contractors who have been pre-qualified. Solicitation documents shall be dispatched together with the invitation, or an indication shall be made in the invitation as to the place and deadline for receiving the documents. Procurement procedures set forth in Chapter Two, Section II,

this Law shall be used for preparing the solicitation documents, submitting and evaluating tenders. 3. The invitation to pre-qualify must contain the following information: 1) the name, code, address, telephone and fax numbers

the contracting authority; 2) the object

procurement and is description; 3) the manner, place and deadline for the receipt

pre-qualification documents; 4) the language/languages in which pre-qualification documents are prepared; 5) the price (if any) charged by the contracting authority for pre-qualification documents, and the payment procedure. The price shall reflect the actual cost

copying the pre-qualification documents and providing them to the suppliers/contractors. Additional payment may be charged for the translation

documents into a foreign language, comprising the costs

translation; 6) the place and time for the submission

applications to pre-qualify, the number

suppliers/contractors that will be pre-qualified; 7) other information prescribed by the Public Procurement

fice. 4. The time limit for the submission

applications to pre-qualify, set by the contracting authority, may not be shorter than 15 days and in cases where the tender notice is published in a publication with international circulation or specialised publication - not shorter than 35 days after the publication

the invitation to tender. 5. The time limit for the submission

tenders laid down by the contracting authority may not be less than 30 days and in cases where the tender notice is published in a publication with international circulation or specialised publication - not less than 40 days after the day

dispatch

invitations to tender to the selected suppliers/contractors, unless there has been a prior publication

tender notice according to the procedure and terms set forth in Article 12

this Law. In such cases the time limits for the submission

tenders may be reduced accordingly to 20 and 26 days. 6. If less than 3 tenders are received within the time limit fixed by the contracting authority for the submission

tenders, or, if after rejection

tenders in conformity with the requirements

Article 26

this Law, less than 3 tenders are left, the restricted tendering procedure shall be considered not to have taken place and a notice to the effect shall be within 3 working days sent to the suppliers/contractors who submitted their tenders. SECTION IV NEGOTIATED PROCEDURE Article 28. Conditions

Negotiated Procedure 1. Negotiated procedure may be announced where there is at least one

the following conditions: 1) because

the character and complexity the object

procurement it is not feasible to formulate detailed specifications for the object in order to engage in open or restricted procedure; 2) tendering by open or restricted procedure has not taken place as only 2 tenders have been received; 3) tendering by open or restricted procedure has not taken place since all tenders were rejected as being not in conformity with the requirements

the solicitation document

the open or restricted procedure. 2. Where procurement is engaged in by the contracting authorities specified in paragraph 1

(3)

Article 1

this Law, the negotiated procedure may be chosen without complying with the conditions provided for in paragraph 1 hereof. 3. In the case specified in paragraph 1

(2)hereof the contracting authority may, without publishing invitations for submission

initial tenders for negotiated procedure, engage in negotiated procedure with two suppliers/contractors who have submitted tenders. In such case negotiations shall be engaged in following the procedures indicated in paragraph 4

Article 29

, Articles 30 and 31

this Law, without substantially changing the terms

procurement. Article 29. Selection

Suppliers/Contractors for Negotiations 1. For procurement by using negotiated procedure, the contracting authority shall call upon the suppliers/contractors in the manner specified in Article 12

this Law to submit initial tenders to take part in the selection for participation in the negotiated procedure. The invitation to submit initial tenders must contain the following information: 1) the name, code, address, telephone and fax numbers

the contacting authority; 2) description

the object

procurement, giving technical and other specifications. When works or services are procured, the place

their performance or provision shall be indicated; 3) the documents confirming the qualification data to be presented by the suppliers/contractors; 4) the language/languages in which tenders shall be prepared; 5) criteria and conditions

tender evaluation; 6) the place and deadline for submission

tenders; 7) reference to the prior indicative notice

the negotiated procedure to be held, published in the information supplement to the publication “Valstybës þinios” - “Informaciniai praneðimai” and/or in the publication with international circulation or specialised publication; 8) other information prescribed by the Public Procurement

fice. 2. The time limit for the submission

initial tenders fixed by the contacting authority may not be less than 15 days from the day

publishing

the invitation and in cases where a notice

negotiated procedure is published in the publication with international circulation or specialised publication, the time limit may not be less than 37 days from the date

publishing

the invitation. 3. Upon evaluating, according to the criteria set forth in the invitation, the qualification data indicated by the suppliers/contractors in the initial tenders and the proposed conditions

procurement, the Commission shall select at least 3 suppliers/contractors to be invited to take part in negotiations. Where only 2 initial tenders have been received, the Commission shall invite the suppliers/contractors who submitted the tenders to take part in the negotiation procedure, and in case only one tender has been received, the negotiations and procurement may be carried out in the manner laid down in Article 32

this Law. 4. A written invitation to negotiate dispatched to the suppliers/contractors must contain information on the time, place and proposed language

negotiations. Article

  1. Negotiations with the Selected Suppliers/Contractors
  2. The Commission shall have the right to negotiate with the supplier/contractor the contents

tenders. 2. During the negotiations the following conditions must be observed: 1) the parties must not reveal to any other person any technical, commercial or price-related information; 2) the same requirements must be applied with respect to all suppliers/contractors selected by the Commission; 3) minutes

the negotiations must be taken. The minutes

the negotiations shall be signed by the chairman

the Commission and the Commission members who took part in the negotiations. Article 31. Submission and Evaluation

Final Tenders 1. Having taken account

the negotiation results, the contracting authority shall invite the selected suppliers/contractors to submit final tenders. The invitation to submit final tenders must contain the following information: 1) requirements for the preparation

final tenders; 2) revised description

the object

procurement; 3) the criteria and conditions for the evaluation

tenders; 4) the procedure for discounting the

fered price and the rate

discount; 5) the proposed conditions

the contract; 6) the tender security and the security for the performance

the contract; 7) the language/languages, time limits, place, time, manner

the submission

tenders; 8) the procedure for o 9) opening

envelopes; 9) other information prescribed by the Public Procurement

fice for the supplier/contractors. 2. The time limit fixed by the contracting authority for the submission

final tenders may not be less than 30 days and in cases where a notice

procurement by using negotiated procedure was published in a publication with international circulation or specialised publication - not less than 40 days from the day

dispatch

the invitation to the selected suppliers/contractors, except where a prior notice

the intended procurement by negotiated procedure was published according to the procedure and within the time limits specified in Article 12

this Law. In such cases the time limits for the submission

final tender may be reduced to accordingly 20 and 26 days. 3. The successful tender shall be ascertained according to the procedure set forth in Chapter Two, Section II,

this Law. 4. The security

the final tender

the negotiated procedure and the security for the performance

the contract shall be regulated in the manner laid down in Chapter Two, Section II,

this Law. 5. A notice

the successful tender shall be dispatched to all suppliers/contractors who submitted final tenders no later than within 3 working days after the date

the decision taken by the Commission regarding the successful tender. 6. The contracting authority shall award the contract to the supplier/contractor whose tender has been recognised as the successful tender by the decision

the Commission. SECTION V PROCUREMENT FROM SINGLE-SOURCE

SUPPLY Article 32. Procurement from Single Source

Supply 1. The contracting authority may procure goods, works and services by soliciting an

fer from a single supplier/contractor with whom the contracting authority may engage in negotiations for substance, price

the

fer and terms

contract.. 2. Procurement by single-source procedure shall be allowed if: 1) the goods, works or services are available only from a particular supplier/contractor or a particular supplier/contractor has exclusive rights in respect

the goods, works or services and no reasonable alternative exists; 2) for reasons

extreme urgency, brought about by events unforeseeable by the contracting authorities in question, there is an urgent need for goods, works or services and engaging in tendering procedures or any other procurement procedure would therefore be impractical; 3) the contracting authority seeks to enter into a contract with the supplier/contractor for the purpose or research, experiment, study or development. The provision shall not apply to cases where the contract includes the production

goods in quantities to establish their commercial viability or to recover research and development costs; 4) the contracting authority, having procured goods or services from a supplier/contractor, determines that additional supplies must be procured from that supplier/contractor for reasons

standardisation or because

the need

compatibility with existing goods or services, taking into account the effectiveness

the original procurement in meeting the needs

the contracting authority, also if the price

the additionally procured goods or services does not exceed 30 %

the price

the original procurement, the reasonableness

price

goods or services and other terms are not affected, whereas the alternatives to the goods or services in question would not be suitable for reasons

technical incompatibility with those originally procured; 5) a contract is to be awarded for additional works or services not included initially in the contract first concluded, but which have through unforeseen circumstances become necessary for the performance

the works or services described therein. The award

the contract may be made to the supplier/contractor to whom the main contract has been awarded and the aggregate estimated value

contracts awarded for additional services/works may not exceed 50 %

the amount

the main contract; 6) tendering by open, restricted or negotiated procedure has not taken place as only one tender has been received. In this case the terms announced in the tendering procedure may not be altered, neither may be the tender price increased; 7) a strategic investor/strategic investors invested in the contracting authority not less than LTL 200 m within 3 years (36 calendar months) after 1 October 1998, and the contracting authority has approved the regulations

procurement engaged in by it: 8) the estimated value

goods, services or works to be procured from penal institutions, state-owned enterprises whose founder is the Ministry

the Interior or the Ministry

Justice and which have at least 50%

convicted persons among their employees, or enterprises over 50%

whose employees are persons with limited functional capacity as well as enterprises under health care institutions, at least 50%

whose employees are patients working under programmes

occupational therapy, is less than that specified in paragraph 3

Article 12

this Law, where the goods, services and works to be procured are produced, provided and performed by the above-specified institutions and enterprises. 3. Where the contract value for the procurement

goods or services exceeds LTL 150 000 and

works - LTL 500 000, contracts with single source

supply shall be permitted only if at least one

the conditions provided for in paragraph 2 hereof are present and with the authorisation

the Government

the Republic

Lithuania. The provision shall also apply in cases where the contracting authority engages in procurement awarding contracts to single source

supply according to the terms specified in paragraph 2

(5)hereof, the aggregate estimated value

original contracts for services and contracts awarded for additional purposes exceeds LTL 150 000 and in case

contracts for works - LTL 500 000. The authorisation

the Government

the Republic

Lithuania shall not be required for procurement executed by the Bank

Lithuania with the funds

the Bank. Procurement specified herein shall be executed by the Bank

Lithuania upon the resolution

the Board

the Bank

Lithuania. Undertakings operating in the water, energy, transport and telecommunications sectors shall be required to receive authorisation

the Government

the Republic

Lithuania for the procurement

goods, services or works the value whereof exceeds the value specified in paragraph 1

(3)

Article 1

this Law. The authorisation

the Government

the Republic

Lithuania shall not be required for the procurement

hot and cold water, electricity, heat, gas supplied by pipeline and wire communications services, also for procurement executed by the undertakings operating in the water, energy, transport and telecommunications sectors according to the requirements

paragraph 2

(2)

this Article. The authorisation

the Government shall not be required for the procurement

raw materials, materials, complementary parts, primary energy resources and services relating to the supply thereof, also special equipment and spare parts necessary for the primary activity

the State Enterprise Ignalina NPP. The authorisation

the Government

the Republic

Lithuania shall not be required for the procurement

goods, works or services in the case referred to in paragraph 2

(8)hereof. 4. Procurement under the terms provided for in paragraphs 2
(4)and 2
(5)may be engaged in for a period not exceeding 3 years. 5. In case

procurement contracts with single source

supply, the tender security and the security for the performance

the procurement contract shall be regulated in the manner set forth in Chapter Two, Section II,

this Law.

  1. Upon ascertaining that the supplier’s/contractor’s tender is responsive and the price is justified and acceptable, the Commission shall make a decision to award the contract to the supplier/contractor. SECTION VI REQUEST FOR QUOTATIONS Article
  2. Request for Quotations
  3. Procurement by means

a request for quotations may be engaged in provided that all the following conditions are present: 1) there is a competitive supply on the market

readily available goods or services that are not specially produced or provided to the particular specifications

the contracting authority; 2) the estimated value

procurement contract does not exceed LTL 150 000 within a financial year; 3) the criteria for the evaluation

the object

procurement shall be solely the price. 2. The contracting authority shall request quotations from suppliers/contractors according to the procedure laid down in Article 12

this Law. The request for quotations must contain the following information: 1) name, code, address, telephone and fax numbers

the contracting authority; 2) name, amount, technical and aesthetic, functional and quality requirements

goods, services; 3) place, time limits and terms

supply

goods, provision

services; 4) that all taxes are to be included in the price. The tender price and the charges for additional services indicated in the tender (transportation, insurance, loading charges) are to be calculated and submitted separately; 5) in what manner, to whom and when the tenders are to be submitted; 6) envelope opening procedure, place and time; 7) other information prescribed by the Public Procurement

fice. 3. The time limit for giving price quotations may not be less than 10 days after the date

publishing

request for quotations in the information supplement to the publication “Valstybës þinios” - “Informaciniai praneðimai”. 4 Each supplier/contractor shall be permitted to give only one price quotation. It shall not be permitted to change the quotation. Price quotations shall be given and envelopes shall be opened according to the procedure set forth in Articles 21 and 24

this Law. 5. When procurement is engaged in by means

request for quotations, tender security and security for the performance

the procurement contract shall be regulated according to the procedure established in Chapter One, Section II,

this Law. 6. The Commission shall ascertain the supplier/contractor who gave the lowest-priced quotation, announce him as the successful tenderer in the manner set forth in Chapter Two, Section II,

this Law and draw up the draft procurement contract. The contracting authority shall award the procurement contract to the supplier/contractor. 7. Notice

the successful tender shall be dispatched to all suppliers/contractors who gave price quotations no later than within 3 days after the date

the taking

decision by the Commission. 8. If less than 3 tenders are received by the final date fixed by the contracting authority for the submission

tenders or less than 3 tenders remain upon rejection

tenders in accordance with the requirements

Article 26

this Law, request for quotations shall be considered not to have been issued and a notice to the effect shall be dispatched within 3 working days to the suppliers/contractors who submitted their tenders. SECTION VII AWARD

PROCUREMENT CONTRACT Article 34. Award and Alteration

Procurement Contract 1. The award and termination

procurement contract shall be governed by the Civil Code

the Republic

Lithuania and this Law. 2. If unforeseeable circumstances evolve, the contracting authority, upon being given authorisation

the Public Procurement

fice, shall have the right to terminate all procurement procedures prior to the award

the procurement contract. The contracting authority shall publish a notice to the effect in the information supplement to the publication “Valstybës þinios” - “Informaciniai praneðimai”. 3. The contracting authority must award the contract

procurement to the supplier/contractor whose tender is recognised as the successful tender by the Commission and to the supplier/contractor specified in paragraph 6

Article 32

this Law. The successful tenderer shall be notified in writing that its tender has been recognised as the successful tender and be indicated the date by which it is to arrive and sign the procurement contract. 4. If the supplier/contractor, who has been given a proposal

contract award, refuses the award in writing or fails to present security for the performance

the procurement contract prescribed by contract documents or fails to come to sign the procurement contract by the date indicated by the contracting authority, it shall be deemed to have refused the award

the procurement contract. In such event the Commission shall propose awarding the contract to the supplier/contractor whose tender in the descending order

tenders approved by the Commission is next after that

the successful tenderer who refused the contract award. 5. When awarding the procurement contract, the price given in the successful tender, the object

the tender, the requirements for the security

the performance

the contract may not be altered. 6. After the award

the contract the contracting authority shall within 3 working days dispatch a notice

the results

the award procedure. The notice shall indicate the tenderer to whom the contract is awarded, the object

the contract, the price given in the contract and the discounted price. 7. It shall be prohibited to increase the price

procurement throughout the contract validity period or to modify the essential terms

the awarded procurement contract laid down during the tendering procedure, except in cases where the price

procurement is affected by the changes in taxation or where there is an at least 10% change in the market price

goods and services and this could not have been foreseen when awarding the procurement contract. In the above cases the contracting authority must receive the authorisation

the Public Procurement

fice. The contracting authority may also increase the price

procurement taking into account the price indexation to mitigate inflation in the second and subsequent years, where the awarded contact is for the construction

the entire facility, the duration whereof is over 1 year. SECTION VIII REPORT ON THE PROCUREMENT PROCEDURES Article

  1. Report on the Procurement Procedures
  2. The contracting authority shall within 10 days from the award

the contract or the termination

procurement procedures present a report on each contract awarded in accordance with the form approved by the Public Procurement

fice. The report shall include: 1) the name, code, address, telephone number

the contracting authority; 2) short description

the object

procurement and value

the contract; 3) the names and addresses

the suppliers/contractors who submitted tenders; 4) professional qualifications

the suppliers/contractors who took part in the procurement procedures; 5) price

every tender; 6) description

tender evaluation and comparison and the conclusion

the Commission regarding the successful tender, the name

the successful tenderer (supplier/contractor) and motives for the selection

the tender; 7) where procurement procedure used was other than tendering, grounds for the use thereof; 8) if tenders were rejected - grounds for their rejection; 9) other information prescribed by the Public Procurement

fice. 2. The information specified in subparagraphs 2 and 3

paragraph 1 hereof shall be furnished to every person who requests for it. 3. The information specified in subparagraphs 4-8

paragraph 1 hereof shall be furnished to the suppliers/contractors who request for it. 4. The contracting authority and the Commission shall have no right to release information on the contract performance where the release would be contrary to law, would prejudice the legitimate commercial interests

third parties or might prejudice fair competition. 5. The performed procurement contracts, minutes and other procurement related documents shall be preserved in the manner prescribed by the Law

the Republic

Lithuania on Archives. CHAPTER THREE EXAMINATION

COMPLAINTS AND PAYMENT

DAMAGES Article 36. The Right

the Supplier/Contractor to File a Claim or Lodge a Complaint about the Actions or Decisions

the Contracting Authority 1. Every supplier/contractor who has an interest in procurement and believes that the contracting authority has not complied with the requirements

this Law and violated his lawful interests, shall have the right to file a claim or lodge a complaint about the actions or decisions

the contacting authority in the manner and within time limits set forth in Articles 37-41

this Law, prior to the adoption by the Commission

the decision on the successful tender. 2. The supplier/contractor who objects to the Commission’s decision regarding the recognition

the successful tender or believes that the awarded procurement contract violates his lawful interests shall have the right to apply to court in the manner established by law. Article 37. The Procedure and Time Limits for the Filing and Examination

Claims 1. Claims shall be filed with the contracting authority in writing within 5 days from the day the supplier/contractor became aware or should have become aware

the violation

his lawful interests. 2. The contracting authority shall review only those claims

the suppliers/contractors which have been received before the adoption by the Commission

the decision on the successful tender. 3. Upon receiving the supplier’s/contractor’s written claim, the contracting authority shall suspend procurement procedures until the claims are fully examined and a decision is taken. Procurement procedures shall not be suspended upon receipt

the authorisation

the Public Procurement

fice if, upon suspension

the procurement procedure, the supplier/contractor would sustain much heavier losses than those which could be sustained by the supplier/contractor who filed the claim. 4. The contracting authority must extend the time limits

procurement procedures for the period

suspension

procurement procedures. After a decision on the claim is taken the procurement procedures shall be continued. In case the time limits

procurement procedures notified to the suppliers/contractors are changed due to consideration

claims, the contracting authority shall dispatch to suppliers/contractors a notice to the effect, indicating the reasons for the extension

time limits. 5. The contracting authority must examine the claims and take a justified decision within 5 days

the receipt

the claim as well as notifying the supplier/contractor who filed the claim

the taken decision not later than on the next working day. 6. If the contracting authority fails to consider the claims within the time limit specified in paragraph 5 hereof, or rejects the claims, the supplier/contractor may file a complaint with the Public Procurement

fice. Article

  1. Procedure and Time Limits for Filing Complaints
  2. The supplier/contractor shall have the right to file a complaint with the Public Procurement

fice without filing a claim with the contracting authority. 2. The complaint shall be filed within 10 days from the day when the supplier/contractor became aware or should have become aware

the violation

its lawful interests or within 5 days from the receipt

the decision

the contracting authority on the examination

the claim or, in case the decision was not received, within 5 days

the expiry

the time period set in Article 37

this Law for the examination

claims. 3. Upon receipt

the supplier’s/contractor’s complaint, the Public Procurement

fice shall organise examination

complaints at the Independent Commission for the Examination

Complaints Relating to Public Procurement. 4. Upon receipt

the supplier’s/contractor’s complaint, the Public Procurement

fice must not later than on the next working day notify the contracting authority

the receipt

the complaint. Upon receipt

the notification

the Public Procurement

fice regarding the complaint filed by the supplier/contractor, the contracting authority must suspend procurement procedures. The procedures shall be resumed only upon authorisation

the Public Procurement

fice. 5. The contracting authority must extend the time limits

procurement procedures for the period the procedures are suspended. If the time limits

procurement procedures

which the suppliers/contractors were earlier notified are extended by reason

the complaint examination, the contracting authority shall send a notice to the effect to other suppliers/contractors and specify the reasons for the extension

the time limits. Article 39. Form and Contents

Complaints 1. Complaints shall be filed with the Public Procurement

fice in writing. The complaint shall indicate: 1) the name, address and code

the supplier/contractor; 2) the name, address and code

the contracting authority the actions or decisions whereof are the object

complaint; 3) unlawful actions or decisions

the contracting authority and the legal acts or circumstances which prove the unlawfulness thereof; 4) full name

the member

the Independent Commission for the Examination

Complaints Relating to Public Procurement, selected by the supplier/contractor; 5) the requirements

the supplier/contractor.

  1. The supplier/contractor shall attach to the complaint the documents substantiating the complaint. Article
  2. Independent Commission for the Examination

Complaints Relating to Public Procurement 1. The Independent Commission for the Examination

Complaints Relating to Public Procurement (hereinafter referred to as the Independent Commission) is a Commission for the examination

complaints filed by the suppliers/contractors, whose functioning is governed by this Law and the regulations approved by the Government

the Republic

Lithuania. 2. Candidates to the members

the Independent Commission shall be nominated by state and local government institutions, associations, public organisations. 3. The Public Procurement

fice shall draw up and approve the list

the Independent Commission members from the nominated candidates, to be published in the supplement to the publication “Valstybës þinios”- “Informaciniai praneðimai”. 4. The requirements for the members

the Independent Commission and the requirements for the drawing up

their list (the entry

members on the list and their removal form the list) shall be laid down by the Public Procurement

fice. 5. The procedure

remuneration

the Independent Commission members for their work and the procedure for covering the costs

complaint examination at the Independent Commission shall be established by the Government

the Republic

Lithuania. Article 41. The Procedure and Time Limits

Complaint Examination 1. The Independent Commission shall examine only those complaints

the suppliers/contractors which are received prior to the adoption

the decision by the Commission regarding the successful tender and filed in compliance with the requirements

Articles 38 and 39

this Law. 2. The complaints shall be examined by 3 members

the Independent Commission,

whom the supplier/contractor, the contracting authority and the Public Procurement

fice shall each select one member from the list

the Independent Commission members provided for by Article 40

this Law. The Public Procurement

fice shall appoint the Chairman

the Independent Commission from the selected members. 3. Upon receipt

a complaint the Public Procurement

fice shall within 3 days address the contracting authority requesting that the latter select, within a 3-day period, a member

the Independent Commission. If the contracting authority fails to select a member within the prescribed time period, the member

the Independent Commission shall be appointed by the Public Procurement

fice. 4. The Independent Commission must examine the complaint within 20 days from the receipt thereof by the Public Procurement

fice. The Public Procurement

fice may extend the time limit for the examination

the complaint for no longer than 20 days.

  1. Upon examining the complaint, the Independent Commission shall have the right to: 1) refuse to meet the complaint and dismiss it; 2) meet the complaint and obligate the contracting authority to cancel or alter the decisions or actions; 3) meet the complaint and terminate the procurement procedures.
  2. After the Independent Commission makes decisions provided for in subparagraphs 2 and 3

paragraph 5 hereof, the Public Procurement

fice, if it believes that the elements

crime are present, shall notify the State Control or the appropriate law enforcement institutions thereof. 7. The conditions and procedure

complaint examination and removal

the Independent Commission members from complaint examination shall be established by the Government

the Republic

Lithuania . Article 42. Appealing against the Actions

the Public Procurement

fice and the Decisions

the Independent Commission The supplier/contractor and the contracting authority shall have the right to appeal to court according to the procedure prescribed by law against the actions

the Public Procurement

fice and the decisions

the Independent Commission. Article 43. The Right

the Supplier/Contractor to Recover Damages If the contracting authority fails to fulfil the requirements set forth by this Law and other legal acts or violates the supplier’s/contractor’s rights, the supplier/contractor shall have the right to bring an action for damages. Article 44. Liability

the Supplier/Contractor If the supplier/contractor presents forged documents or false data to the contracting authority or fails to fulfil the requirements

this Law and other legal acts, the contracting authority may sue the supplier/contractor for damages in accordance with the procedure established by law. Article 45. Liability

the Executives or other Authorised Persons

the Contracting Authority The executives or other authorised persons

the contracting authority (Commission members and experts) who violate this Law shall be held liable in accordance with the procedure established by law. CHAPTER FOUR FINAL PROVISIONS Article 46. Coming into Effect

the Law 1. The Law shall come into effect as

1 October 1999, except for CHAPTER THREE which shall come into effect as

1 January

  1. Procurement, a notice whereof was announced (by publishing an invitation in the press or dispatching the same to the suppliers/contractors) prior to the coming into effect

this Law, shall be performed and complaints, received prior to the coming into effect

Chapter Three

this Law shall be examined in accordance with the provisions

the Law

the Republic

Lithuania on Public Procurement No.I-1491, enacted on 13 August 1996.” I promulgate this Law passed by the Seimas

the Republic

Lithuania PRESIDENT

THE REPUBLIC VALDAS ADAMKUS