Objecting to a neighbour's planning application in Malta
A site notice on the façade next door, an extra two floors on the plan, a terrace that will overlook your yard: in Malta the right moment to act is while the development application is still before the Planning Authority. Under article 71(6) of the Development Planning Act (Cap. 552) any person may declare an interest in an application and make representations on environmental and planning grounds. Doing so in time makes you a registered interested party: you are told about fresh drawings, the case officer's report and the Planning Board sitting, and, above all, you keep the right to appeal a permit to the Environment and Planning Review Tribunal under the Environment and Planning Review Tribunal Act (Cap. 551). Miss the registration period and your objection is null, and with it most of your options. This guide is for owners and tenants affected by a neighbour's project. It walks through the deadlines in the Development Planning (Procedure for Applications and their Determination) Regulations (S.L. 552.13), how to write representations the Board must consider, how to appeal and ask for the permit to be suspended, what it costs, and what you can still do if works start without a permit. Disputes about servitudes, boundary walls or damage are civil matters: a permit is granted without prejudice to third-party rights (art. 72(1) Cap. 552).
Key facts
Deadline
Register your interest within 30 days from publication of the application notice on the Department of Information website, or within 15 days for applications under the summary procedure (Schedule 2); in urgent cases the notice may shorten this to 7 days (reg. 11(2) S.L. 552.13). Periods do not run from 23 December to 1 January, in the week before Easter Sunday and from 8 to 22 August (reg. 16 and Schedule 4).
An appeal to the Environment and Planning Review Tribunal must be lodged within 30 days from publication of the decision on the Department of Information website (art. 13(1) Cap. 551). A further appeal on a point of law lies to the Court of Appeal (Inferior Jurisdiction) within 20 days from the Tribunal's decision being delivered in public (art. 52).
What to do
Identify the application and the deadline that applies.
Every application is published on the Department of Information website together with the applicant's name and advertised by a notice affixed on site, which the applicant must keep in place for the period it states; local councils also publish the list of applications in their locality (reg. 6 S.L. 552.13). Note the application number (PA/…), the date of publication and whether the case falls under the summary procedure of Schedule 2. Download the drawings and the development profile from the Authority's online system. If the notice was not displayed, photograph the site with dates: a missing notice is relevant to a later appeal on a procedural error (art. 11(3)(b) Cap. 551).
Register your interest in time and in the right form.
The declaration of interest must reach the Authority within 30 days of publication, or 15 days for Schedule 2 applications (reg. 11(2) S.L. 552.13). It may be sent by any written or electronic means, in Maltese or English, and must include an email address, which the Authority will use for all further communications and for notification of the decision (reg. 11(3) and (4)). A declaration received outside the period is null and may not be considered (art. 71(6) Cap. 552). Quote the application number exactly: submissions with a wrong reference number are not considered (reg. 12(8)). If the last day falls on a public holiday or a closure day, the time limit moves to the next working day.
Base your representations on planning and environmental grounds.
The Planning Board decides by reference to approved plans and policies, regulations, other material considerations such as environmental, aesthetic and sanitary ones, and the representations received (art. 72(2) Cap. 552). Point to the specific policy, local plan zoning, height limitation or conservation designation the project breaches, and explain the concrete effect: loss of light to a courtyard, overlooking, a façade out of character in an urban conservation area, an inaccurate site plan. Objections that the neighbour lacks title or will breach a servitude are not decided by the Board, because a permit does not guarantee title and is without prejudice to third-party rights (art. 72(1)). For complex projects a perit's technical note carries weight.
Follow the file until the Planning Board sitting.
As a registered interested party you must be sent any revised drawings within five days of their receipt and told when the case officer's report is completed; you then have ten days to make representations on that report (reg. 12(6) S.L. 552.13). The notification also gives the date of the Planning Board sitting (reg. 12(7)). Late submissions are rejected (reg. 12(8)). Board meetings are public, and the Board must allow the applicant and interested third parties who made representations under article 71(6) to make submissions. Attend, or send a representative, and summarise your strongest planning points in a few minutes; the Board must give reasons for a refusal or for any conditions it imposes (art. 72(1) Cap. 552).
Check the decision as soon as it is published.
The publication date of the decision is set no later than fifteen days after the decision, and the decision notice is communicated to registered interested parties within fifteen days (regs 6(6) and 13(7) S.L. 552.13). The appeal period runs from publication on the Department of Information website, not from the day the email reaches you (reg. 13(8)), so monitor the website. Only the applicant may ask the Board to reconsider a decision, and only on a fine or a condition; a registered interested party cannot request reconsideration even if it objected in writing (art. 76(4) Cap. 552; reg. 14). Your remedy against an approval is an appeal to the Tribunal.
Lodge an appeal with the Environment and Planning Review Tribunal within 30 days.
A registered interested third party may appeal from a decision on a development application (art. 11(1)(e) Cap. 551). The appeal is an application that refers to the decision, sets out each head complained of with reasons, states how the decision should be varied and attaches the relevant documents (art. 15); witnesses must be listed with the facts each will prove (art. 17). Grounds may include a material error of fact, a material procedural error or an error of law (art. 11(3)). You need not prove a juridical interest, but your grounds must be reasoned on environmental or planning considerations (art. 22(1)). You may be represented by an agent (art. 18) and may ask to view the Authority's files (art. 19).
Pay the appeal fee and keep the receipt.
An appeal against a decision on a development permission is accompanied by a fee of 5 % of the Development Permit Fee, with a minimum of €150 and a maximum of €3,500, plus an administrative fee (reg. 3 and Schedules 1 and 2 S.L. 552.21). An appeal is null if the fee is not paid within the time the Tribunal sets (reg. 5). If you win, the fee paid by an interested person is reimbursed in equal shares by the parties cast, and the Tribunal's decision is an executive title for that amount (reg. 7). Site inspections requested by a party carry a separate fee (art. 44 Cap. 551). An appeal declared frivolous or vexatious can lead to a fine of €2,500 (art. 43).
Ask for suspension of the permit if works would cause irreversible harm.
Most permits are automatically suspended until the appeal period in article 13 of Cap. 551 has lapsed (art. 72(3) Cap. 552). To keep the permit suspended during the appeal, file a request for suspension together with the appeal; it cannot be made later (art. 33(1) Cap. 551). The Tribunal hears and decides the request within thirty days and suspends only if, without suspension, the prejudice would be disproportionate compared with the prejudice of stopping the works; it refuses if the development can easily be removed or reversed, or if the request is frivolous (art. 33(2) and (3)). A suspension lasts at most three months from the first hearing, and the Tribunal must then decide the merits within that time (arts 33(5) and 34).
Take part in the hearing, then consider a further appeal.
Without a suspension request, the first hearing is held within two months of the appeal, on at least fourteen days' notice (art. 23 Cap. 551), and the final decision is due within one year of the first hearing, extendable once by six months (art. 35). The Tribunal may confirm, revoke or alter the decision (art. 31). If it is the applicant who appeals a refusal, you are informed and may register in the appeal within five working days (art. 21). The Tribunal's decision is final except on a point of law or a breach of fair hearing (art. 39); such an appeal goes to the Court of Appeal (Inferior Jurisdiction) within twenty days of the decision being delivered in public (arts 50 and 52).
If works start without a permit, or the permit was obtained on false information, report it.
Where development is carried out without a permit, against its conditions or in breach of the Act, the Executive Council issues a stop notice, and may issue enforcement notices requiring removal (art. 97 Cap. 552). Report the works to the Planning Authority's enforcement section with photographs, dates and the address. If a permit was granted on fraud, on an incorrect site plan or declaration, or through an error on the face of the record, any person may request its revocation or modification (art. 80(1)); the person who made the request may appeal the Board's decision to the Tribunal within thirty days of the hearing (art. 80(3)). Claims for damage, nuisance or breach of servitude go to the civil courts.
What to watch out for
- Missing the registration period: a declaration of interest received late is null (art. 71(6) Cap. 552), and without registration you cannot appeal the permit as an interested third party.
- Counting the 30 days from the email notification of the decision: the appeal period runs from publication on the Department of Information website (art. 13(1) Cap. 551; reg. 13(8) S.L. 552.13).
- Objecting only on private-law grounds such as title, servitudes or a party wall: the Board does not decide them, because permits are granted without prejudice to third-party rights (art. 72(1) Cap. 552).
- Forgetting to request suspension in the appeal application itself: the request can be made only concurrently with the appeal (art. 33(1) Cap. 551), and works may proceed once the automatic suspension lapses.
- Quoting the wrong application number or using an email address you do not check: such submissions are not considered, and the Authority sends every later notice, including the decision, to the email address you registered (regs 11(3)–(4), 12(8) S.L. 552.13).
- Filing a weak appeal to delay a neighbour: the Tribunal may declare it frivolous or vexatious and fine the appellant €2,500 (art. 43 Cap. 551).
- Ignoring the closure periods: they suspend the regulatory time limits, but they do not suspend the 30-day appeal period in the Tribunal Act; do not rely on them for the appeal without checking.
Legal basis
Frequently asked questions
How long do I have to object to a planning application in Malta?
You must register your interest within 30 days from publication of the application notice on the Department of Information website, or 15 days for applications under the summary procedure in Schedule 2 of S.L. 552.13. In urgent cases the notice may shorten the period to seven days (reg. 11(2)). Late declarations are null (art. 71(6) Cap. 552).
How do I submit an objection to the Planning Authority?
Send a written or electronic declaration of interest with your representations, in Maltese or English, quoting the exact application number and giving an email address (reg. 11(3) S.L. 552.13). Electronic submission through the Authority's online system is accepted (reg. 11(3); art. 71(8) Cap. 552). Keep proof of the date of submission, because late or wrongly referenced submissions are rejected.
What are valid grounds to object to a building permit in Malta?
Grounds must be relevant to environment and planning (art. 71(6) Cap. 552): breach of the local plan or policies, height limitations, overlooking and loss of light, character of an urban conservation area, heritage, sanitary or traffic impacts, or inaccurate drawings. Title disputes and servitudes are civil matters outside the Board's remit (art. 72(1)).
Can I appeal a planning permit granted to my neighbour?
Yes, if you registered as an interested party during the application. You may appeal to the Environment and Planning Review Tribunal within 30 days from publication of the decision (arts 11(1)(e) and 13(1) Cap. 551). You need not prove a juridical interest, but your grounds must be reasoned on planning or environmental considerations (art. 22(1)).
How much does a planning appeal cost in Malta?
The Tribunal fee for an appeal on a development permission is 5 % of the Development Permit Fee, at least €150 and at most €3,500, plus an administrative fee (S.L. 552.21, Schedules 1 and 2). Site inspections requested by a party cost extra. If an interested person wins, the parties cast reimburse the fee (reg. 7). Lawyer or perit fees are separate.
Can works start while my appeal is pending?
Most permits are suspended automatically until the 30-day appeal period has lapsed (art. 72(3) Cap. 552). After that, works may proceed unless you asked for suspension in your appeal application and the Tribunal granted it (art. 33 Cap. 551). The Tribunal decides the request within 30 days, and a suspension lasts at most three months from the first hearing.
Can I ask the Planning Board to reconsider its decision?
No. Reconsideration is available only to the applicant and only on a fine or condition, within 30 days of publication (reg. 14 S.L. 552.13). A registered interested party cannot request reconsideration even after objecting in writing (art. 76(4) Cap. 552). Your remedy is an appeal to the Tribunal.
How long does the Environment and Planning Review Tribunal take?
The first hearing should be held within two months of the appeal (art. 23 Cap. 551). Without a suspension, the final decision is due within one year of the first hearing, extendable once by six months (art. 35). If the permit is suspended, the Tribunal must decide within three months of the first hearing (art. 34).
Is the Tribunal's decision final?
Largely yes. Article 39 of Cap. 551 allows an appeal only on a point of law decided by the Tribunal or on a breach of the right to a fair hearing. It goes to the Court of Appeal (Inferior Jurisdiction) within 20 days from the decision being delivered in public (art. 52). Factual and policy assessments cannot be reopened there.
My neighbour is building without a permit. What can I do?
Report the works to the Planning Authority's enforcement section with photos, dates and the exact address. The Executive Council issues stop notices and enforcement notices for development without a permit or in breach of its conditions (art. 97 Cap. 552). If a permit exists but was obtained on false plans or declarations, you may request its revocation (art. 80).